Presentation is loading. Please wait.

Presentation is loading. Please wait.

Applied Science University

Similar presentations


Presentation on theme: "Applied Science University"— Presentation transcript:

1 Applied Science University
Quantity Take Off Dr. Ayman A. Abu Hammad

2 Topical Overview Chapter 1: Site Preparation
Chapter 2: Soil and Site Exploration Chapter 3: Excavation Chapter 4: Foundations Work Chapter 5: Wood Formwork Chapter 6: Steel Rebar Chapter 7: Concrete Chapter 8: Building structures Chapter 9: Walls Construction Chapter 10: Brick Works Chapter 11: Masonry (Stone) Chapter 12: Stair Wells

3 2-3-4… Floor X Letter of intent Foundations rebar fabrication
Mobilization: Site offices Off. furniture Computer, phone, Workers residence Cement-agg.-rebar Sto. Tools & equip. Security fence Planning: Schedule Project team Subcontractors Suppliers Submittals workforce Site electricity, access roads, phone line, water, heat Cars Notice to proceed Civil Works RC foundations forms- rebar Foundations center lines Blinding forms- cast Foundations RC cast Excavation: 1- Bulk Exc. 2- Trimming Found. Wall forms- rebar 2-3-4… Found. wall cast Floor X Columns forms- rebar Compacted backfill Finishing Side walks Masonry Partition walls- block work Dismantle slab 1 forms Retaining Walls, fence Slab # 1 forms- rebar Floor on grade: rebar- cast Slab # 1 cast Cast column & walls 2- Weeks E&M rough RC walls: forms-rebar cast Plaster Tile Doors-wind. Paint

4 Rebar Take-off Rules Steel diameters are: Rebar Standard Lengths are:
8, 10, 12, 14, 16, 18mm…. Rebar Standard Lengths are: 4, 5, 6, 7, 12m. Overlap standard distance is= 40*max Diameter for tension, 50*max Diameter for compression. Cover distance = 0.005m in foundations only and 0.025m otherwise. Stirrup key is 0.1 *2= 0.2m Rebar order format is as follows: Calculated Number Ø Standard Diameter/ Standard Length Rebar volume is negligible in concrete quantity take-off. AGGREGATE REBAR DATA FOR SIMILAR DIAMETERS AND LENGTHS ONLY! FOR TONNAGE ESTIMATION MULTIPLY THE NUMBER BY THE LENGTH BY THE UNIT WEIGHT OF BAR. SHOULD TRANSLATE TAKE-OFF NUMBERS ON THE A-CADS. Rebar Steps: Foundations: Strip, Isolated, Tie beams, FW Floors, Columns, Walls, Retaining Walls, lintels Slabs: P Beams, S Beams, Double Rib, Wall Beams, Ribs

5 3.5m 0.35m 7 D14mm/1m Wall height=3m 5D16mm/1m 4 D12mm/1m 5 D14mm/1m 0.4m 0.25m 4.8m

6 3.5mx4.5mx3m interior dim. Reservoir
Overlap=40*max diam.= 0.64m Foundation: Stirrups: [( )*2]+[( )*2]+0.2= 10.3m Res. Length= =5.8m [5.8*5]+1= 29 +1=30 stirrup 30D16/5m+30D16/6m Longitudinal: Top bars= 4.8*7= 34 bar, length= =5.8m 6m 68D14/6m Walls: Vertical: length= 2.95m = 3.5m Wall perimeter={2*(3.5+[0.25 C-C])}+{2*(4.5+[0.25C-C])}= 17m Number of longitudinal bars= 17m*8bars per meter= 136 bar 136D12/7m Short wall length= 3.5+(0.25*2)= 4m Long wall length= 4.5+(0.25*2)= 5m Number of longitudinal bars= 3m*10*2= 60 120D14/4m 120D14/5m 6m 5m 0.64

7 Concrete for Water Reservoir

8 Isolated Foundation 2.5m*3m*0.45m & Column0.25m*0.6m. FWH=1.3m
Stirrups: (2*[( )+( )])+0.2= 5.9m6m Number of stirrups= 3m*5stirrups per meter= 15+1=16 16D16/6m Longitudinal: (2*[( )+( )*2])+0.2= 6.9m7m Number of stirrups= 2.5m*7stirrups per meter= 18 17D14/7m Column C1: Column Dowels: length= (overlap=40*16mm=0.65m)= 2.70m 3m 8D16mm/3m 4D16mm/6m C1 above FL= 3.12(12 stones height)+0.3(slab)+0.64(overlap)= 4m 8D16/4m 0.65 overlap 8D16mm 7D8mm/1m Wall height=1.3m 5D16mm/1m 0.45m 7 D14mm/1m 1.125m 0.25m 1.125m 2.5m

9 Civil Drawings (Foundations Drawings)
1

10 Civil Drawings (Foundations Drawings)
1 TB TB TB f1c1 f1c1 TB TB TB

11 Civil Drawings (Foundations Drawings)
9.5 6 S1-1 1 4.00 S1-1 S1-1 3 3 3 7 6 5 S2-2 S1-1 3.5 TB TB 5 TB 4.6 S2-2 f1c1 f1c1 3.5 9.50 TB TB TB 4 5m 4 S2-2 TB S2-2 TB S3-3 5 S3-3 7 S2-2 7 5 13m 3.7

12 Strip Footings 0.2 0.3 5Q12/1m 0.40 6*16mm/1m 5*14mm/1m 0.50 10*12mm
0.60 12*14mm 0.10 0.10 0.10 0.10 1.4 0.10 0.10 1.6 S1-1 (Stair Case) S2-2 (Stone) 0.2 5*12mm/1m 0.50 6*12mm 0.10 0.10 0.10 1m S3-3 (Balcony)

13 Strip foundations Rebar S1-S1
S1-S1: 2 strips /6m& 2 strips/ 3m=3 strips length 6m Stirrup length: [( )*2+( )*2] + 0.2= 3.80= 4.00m Stirrup count (compute length of foundation center to center): [(6m-1.4)*2+ (3-1.4)*2]=12m Count= 12*5 stirrups/m= 60 60Q12/4m Longitudinal rebar: 3*10 Q12/6= 30Q12/6m

14 S2-S2 Longitudinal Rebar: 1 strip of length 4m 2Q12/4 12Q14/4 3 strips of length = 5m 2*3stripsQ12/5= 6Q12/5 12*3stripsQ14/5= 36Q14/5 4 strips of length 7m 2*4Q12/7= 8Q12/7 12*4Q14/7= 48Q14/7 Stirrups: 1) [( )*2+( )*2]+0.2= 5m 2) [(1-0.05)*2+( )*2)]+0.2= 2.6= 3 S1-S1 length Center to center= 38m 1) 38*6Q16/5= 228Q16/5m 2) 38*5Q12/3= 190Q12/3= 95Q12/6 0.3 5Q12/1m 0.40 6*16mm/1m 0.60 12*14mm 0.10 0.10 0.10 1.6 S2-2 (Stone)

15 Square Isolated Footings
0.3 1.3m 6*16mm/1m two way 5*8mm/1m 3.2m 6*14mm 0.20 0.60 0.50 0.10 CW1 0.10 0.10 2.6m F1 5*12mm/1m 5*8mm/1m 0.60 6*12mm 6*16mm 0.30 0.60 0.30 C1 Tie Beam TB

16

17 Civil Drawings (Roof Drawings) 4
B1 10*16/4 2*18/7 7*16/5 4*14/12 6*16/6 B2 12*16/4 8*16/7 8*14/5 8*14/6 B3 8*18/8 4*14/6 3*14/6 SB 0.20 40 SB SB SB SB SB B2 B2 2*10 CR SB SB 2*12/3m B1 2*10 B1 B1 B1 SB SB B2 B2 DR 2*10 DR B3 B3 SB SB

18 2*8/20cm 3*18/3.5m 5*16/4m 5*16/2.5m 4*16 5*16 5*16 8*16 4*16 4*14 3*14 6*16 4*14 0.3 3m 5m 5.5m 2.5m 1.00m B1 (1:15) B1 (1:100) *8/20cm 2*8/20cm 0.3 6*16 6*16/4m 4*16 6*16 4*16 B1 10*16/4 2*18/7 7*16/5 4*14/12 6*16/6 B2 12*16/4 8*16/7 8*14/5 8*14/6 B3 8*18/8 4*14/6 3*14/6 4*14 0.30m 4*14 0.3 SB (1:15) 5. m 4m 1.00m *8/20cm B2 (1:15) B2 (1:100) 0.3 4*16 0.30m 2*8/20cm DR&CR (1:15) 8*18/8 6*16 4*14 4*14 6*14 0.3 Roof Details 5. m 2.5m 1.00m B3 (1:15) B3 (1:100)

19 Slab Rebar

20 3.5 3.00 2.5 2.5 5.0 3.7 4.35 2.9 1.1

21 Masonry Types: Zawyah: 1 Lm per piece
Silah: Araqa & Kalb: 1 Lm per piece Dustour: 2 Lm per piece Marabee’: 4 Lm per piece Roukh: 1 Lm per piece Arch: 3 Lm per piece Balcony: each 1 Lm is taken as 2 Lm Burtash: each 1 Lm is taken as 4 Lm

22 1.00 2.00 1.00 1.00 1.00 1.00 0.50 1.00 1.00

23 Masonry Take off Regular Masonry Take Off: Masonry Pieces Take Off:
4*(9.5-[1+4*0.25])= 30 LM 10 (9.5-[5+10*0.25]= 20 LM 2(9.5-[5+2*0.25]= 8 LM 11(9.5-[2*0.25]= 99 LM Masonry Pieces Take Off: Lintels (Burtash)= 2*(2.2) + 6*(1.20) = = LM Corner Stones= 27*2= 54 Opening corner stone= (10*7)+18= 88

24 Quantity Takeoff: Steel Estimating
Steel bar standard diameters: 8mm, 10mm, 12mm, 14, 16, 18, 20, 32 Steel bar standard lengths: 4, 5, 6, 7, 12 Steel overlapping follow rule 40 * Q If you have two bars of 10mm and 16mm, find the overlap distance? Select the higher diameter and multiply with 40= 16*40=640=64cm Distinguish between different types of steel

25 Working Example: Bathroom Quantity & Pricing:
Given information: 3.6*2*3 Window: 0.7*1.00 Door: 0.8*2.1 Bath tub: 0.7* Ceramic: Ceramic Floor: 2.9*2= 6m2 walls: 11.2*3= 33.6 (33.6-[0.7+(0.8*2.1)])= *0.15= 0.405 = 31.6 Plaster quantity Ceramic walls quantity= = 30.9m2 Ceramic labor cost 12KD for blinding= 12KD 20KD*3days= 60KD Joint filling: 1*12KD skilled rate= 12KD Ceramic material cost= 3KD/m2 *37m2= 111KD Total Cost= = 195KD Plaster:= 31.6m2 Plaster material (fine aggregate) cost= 31.6*0.02*1.1= 0.7m2 *2KD= 1.4KD Plaster cement cost (1:3 means 10 cement bags per m3)= 7bags* 1.350= 9.450 Labor cost:2days*20KD=40KD Total cost= = 51KD


Download ppt "Applied Science University"

Similar presentations


Ads by Google