1 Peco Facet Sewage Water Treatment Plant

2 2 Project: ……………………………………………………...Imisli Olympic Sport Complex Contractor: …………………………………………………………………...AZIMPORT LLC Subcontractor for Sewage Water Treatment: …………..Facet Germany GmbH Date of order: ………………………………………………………………………….April 2011 Facet model: …………………………………………………………………………..STP-16HB Max. design flow rate: …………………………………………………………….40 m³/day Equivalent inhabitants: ……………. 160 persons (Directive: CE 91/271/CEE) Commissioning date: …………………………………………………………… Peco Facet Sewage Water Treatment Plant Project Information

3 3 Peco Facet Sewage Water Treatment Plant Imisli town Republic of Azerbaijan 300 kilometers from capital Baku

4 4 Olympic Sport Complex Imisli, Republic of Azerbaijan Peco Facet Sewage Water Treatment Plant Panorama view Facet STP unit Facet STP unit

5 5 Peco Facet Sewage Water Treatment Plant Waste Waters formed in toilets, showers and/or kitchen flows to the Sewage Water Treatment Plant installed by Facet Facet STP unit Facet STP unit

6 6 Peco Facet Sewage Water Treatment Plant Sewage Water Treatment Plant STP16HB Facet scope: Design, Engineering, Supply of Equipment, Supervision of Installation and Start-up All civil works and sewer network system was made by AZIMPORT LLC (local construction company) –

7 7 Peco Facet Sewage Water Treatment Plant Construction period – July 2011 Azimport LLC - Local Civil company has built Pumper well, Inlet pit, Aeration Chamber and House for the Control Room According to drawings provided by Facet Sport Complex back view Facet checks all constructions Pumper well Control room Aeration Chamber

8 8 Peco Facet Sewage Water Treatment Plant Installation works has been carried out by AZIMPORT LLC under supervision of Facet specialists Installation of Settling and Disinfection Chamber by Crane Installation period – October 2011

9 9 Peco Facet Sewage Water Treatment Plant Installation of Settling and Disinfection Chamber by Crane Installation period – October 2011

10 10 Peco Facet Sewage Water Treatment Plant Installation of the skid to Control Room (PLC, Blower, Recirculation Pump, Ozone Generator) Installation period – October 2011

11 11 Peco Facet Sewage Water Treatment Plant Grinding Pumps (main and stand-by) and Screen Bar into the Pumper Well Installation period – October 2011

12 12 Peco Facet Sewage Water Treatment Plant Piping works, Aeration Diffusers, Outlet Pipe Installation period – October 2011

13 13 Peco Facet Sewage Water Treatment Plant Installation of Bio-Film Media into the Aeration Chamber Installation period – October 2011 General Piping Works

14 14 Peco Facet Sewage Water Treatment Plant Start Up and Commissioning – December 2011 Facet specialists has carried out the operation training course to the staff of Final Customer (Administration of Sport Complex)

15 15 Peco Facet Sewage Water Treatment Plant General Plan

16 16 Peco Facet Sewage Water Treatment Plant Effluent Conditions Ph……………………………………………………6-8 BOD5 ……………………………………………..<25 mg/l COD …..……………………………………………<125 mg/l TSS …………………………………………………<35 mg/l O2 dissolved (aeration chamber) …… mg/l Temperature ………………………………….. Ambient Aspect ………………………………………..…. Odorless and Transparent

17 17 Peco Facet Sewage Water Treatment Plant Opening Ceremony of the Imisli Olympic Sport Complex with participation of his Excellency the President of the Republic of Azerbaijan Mr. Ilham Aliyev

18 18 Opening Ceremony Peco Facet Sewage Water Treatment Plant

19 19 Opening Ceremony Peco Facet Sewage Water Treatment Plant

20 20 Thank you for attention Peco Facet Sewage Water Treatment Plant


Download ppt "Peco Facet Sewage Water Treatment Plant. 2 Project: ……………………………………………………...Imisli Olympic Sport Complex Contractor: …………………………………………………………………...AZIMPORT."

Similar presentations


Ads by Google