Presentation is loading. Please wait.

Presentation is loading. Please wait.

CMPC Project COK+FBL – 1st Align Meeting

Similar presentations


Presentation on theme: "CMPC Project COK+FBL – 1st Align Meeting"— Presentation transcript:

1 CMPC Project COK+FBL – 1st Align Meeting
August,

2 CMPC Project - COK+FBL 1st Align Meeting Agenda
Scope of Supply Project organization Time schedule Milestones – first critical 90 days Project manpower chart – whole project What’s new ? Is anything bigger than ever running before ? Has anything been redesigned from anything running ? Is anything brand new and never been running ? Are there any open scope issues remaining ?

3 CMPC Project - COK+FBL 1st Align Meeting Scope of Supply
Cooking: ADMt/d Two vessel steam-liquor phase digester for Concurrent Compact Cooking™ G2 (CoC G2); Fiberline: ADt/d O2 - Dht – EP- D1, bleaching sequence; EPC Project, including the core and non core equipment, installation materials, supervision and site works as MEI erection, commissioning and start up.

4 CMPC Project - COK+FBL 1st Align Meeting Scope of Supply
DCS APC OTS

5 CMPC Project - COK+FBL 1st Align Meeting Project Organization - Araucária

6 CMPC Project - COK+FBL 1st Align Meeting Project Organization - Sundsvall
PROJECT MANAGER Torbjörn Jacobsson HSEQ coordinator Niklas Castenäs Support functions-technical TECHNOLOGY MANAGER – NA INSTALLATION ENGINEER - NA SPARE PARTS ENGINEER – Susanne Sandgren Support functions-administration PROJECT SECRETARY – Carin Öberg CUSTOMER DOCUMENTATION ENG. – Marie Almkvist PROJECT PURCHASE MGR – Fredrik Åström QC MANAGER. – Peter Strömberg FORWARDER – TBN PROJECT SCHEDULER – NA COST CONTROLLER - NA SITE MANAGER - NA START UP MGR - NA TRAINING MGR - Mona Bergström Lead Project Engineer Team PROCESS DESIGN Jörgen Tegner (Andreas Engelfeldt) PLANT DESIGN Tommy H Karlsson TANK & VESSEL Stefan G Jonsson MACHINE DESIGN NA EL & INSTRUMENT Peter Dahlin PROCESS CONTROL Rune Lindström T. Jacobsson

7 CMPC Project - COK+FBL 1st Align Meeting Project Organization - Karlstad
PROJECT MANAGER Jan-Åke Larsson QEHS coordinator Carina Törngren Support functions-administration PROJECT SECRETARY – Carin Sonesson CUSTOMER DOCUMENTATION ENG. – Catarina Melin/Ann Arnell PROJECT PURCHASE MGR – Cooking – Greger Andersson Recaust - Sten Leandersson TECHNICAL PURCHASE SUPPORT – Anders Holmberg QC MANAGER. – Stefan Bergman FORWARDER – Margareta Sjöman PROJECT SCHEDULER – Fredrik Sundell PROJECT CONTROLLER – Anna Gydemo-Berg Support functions-technical TECHNOLOGY MANAGER – Recaust Magnus Ingelman Cooking: Jonas Saetheråsen INSTALLATION ENGINEER – Mattias Carlsson SPARE PARTS ENGINEER – Truls Snedsböl SITE MANAGER – START UP MGR - TRAINING MGR - Mona Bergström Project Team LPE PROCESS DESIGN Cooking: Jonas Saetheråsen Recaust Magnus Ingelman LPE PLANT DESIGN Stefan Wessmark LPE TANK & VESSEL Kenneth Persson LPE EL & INSTRUMENT Cooking Gunnar Rutquist Recaust Tommy Höök T. Jacobsson

8 CMPC Project - COK+FBL 1st Align Meeting Time Schedule
Digester and Impbin Manufac. Sep.2013 Civil Work Aug.2013 Erection Start Jan.2014 Commissioning Feb Start Up May 2015

9 CMPC Project - COK+FBL 1st Align Meeting Time Schedule
Project schedule 03/May/2013 Contract effective date 18/Aug/2013 Site establishment 22/Jul/2013 18/Sep/2013 Civil Works 09/Aug/2013 18/Jan/2014 Start of erection works 18/Jun/2014 Electrical Room Release 03/Oct/2014 FAT start date 30/Oct/2014 Power on (electrical room) 03/Jan/2015 Training 03/Jan/2015 DCS loaded 03/Feb/2015 Comissioning phase 03/Feb/2015 Digester Hydrotest 03/May/2015 ECA / Start-up

10 CMPC Project - COK+FBL 1st Align Meeting General – S Curve
Jun/13 Jul/13 Ago/13 Sep/13 Prev. 1,67 1,96 2,14 2,33 Real. 1,98

11 CMPC Project -COK+FBL 1st Align Meeting Milestones, first critical 90 days
Engineering Kick off meetings with CMPC & with Metso's technology center Flowsheet and Lay-out in advanced status; Finish specifications for all core equipment, towers & tanks, pumps, ejectors, agitators, heat exchangers, electrical system are completed; Engineering documentation according to App.4 Started Piping Detail Engineering; Time schedule in approving phase; Soil investigation – civil engineering on going

12 CMPC Project - COK+FBL 1st Align Meeting Milestones, first critical 90 days
Procurement - Purchase process completed Core equipment: Digester, ImpBin, HPF, Twinroll Presses, Mixers, MC Pumps Main Tanks & Towers Steel Structure; Electrical system; Civil Engineering & Construction; Plant Design Engineering Centrifugal pumps Presses & Mixers Tanks & Towers Tanks & Towers Tanks & Towers Civil Construction Plant Design Steel Structure Electrical system

13 Shanghai RS Shanghai RS Zhongshan ES RS Vadodara ES Sweden PR
Steel Structures Zhongshan ES RS Vadodara + Liquor Screen L8 + Delta Screens D10 e D4 + Coarse Screen KFA-75 + Tail Screen TS-75 + Delta Knotter K8 ES Sweden + Mixers + Pulp Distributor TMC-60 + Flow Scrapers SA + DeltaCombi DC16 PR Centrifugal pumps

14 CMPC Project - COK+FBL 1st Align Meeting Milestone, first critical 90 days
Metso Sundsvall Morimatsu Intecnial Nova JVA KingSun Imetame

15 CMPC Project - COK+FBL 1st Align Meeting Project manpower chart – Site Activities
Peak: 1000 p

16 CMPC Project - COK+FBL 1st Align Meeting What’s new ?
MC Pump CM 4030

17 CMPC Project - COK+FBL 1st Align Meeting Are there any open scope issues remaining ?


Download ppt "CMPC Project COK+FBL – 1st Align Meeting"

Similar presentations


Ads by Google