LATIN AMERICAN DRILLING SAFETY REPAIR & CERTIFICATION OF BLOW OUT PREVENTERS IN ARGENTINA WILFREDO NUÑEZ JORGE GOLDSACK.

Similar presentations


Presentation on theme: "LATIN AMERICAN DRILLING SAFETY REPAIR & CERTIFICATION OF BLOW OUT PREVENTERS IN ARGENTINA WILFREDO NUÑEZ JORGE GOLDSACK."— Presentation transcript:

1 LATIN AMERICAN DRILLING SAFETY REPAIR & CERTIFICATION OF BLOW OUT PREVENTERS IN ARGENTINA WILFREDO NUÑEZ JORGE GOLDSACK

2 PREAMBLE The essence of Well Integrity is the ability to guarantee the safe containment of pressured subsurface formation fluids during a Well Control. BLOW OUT PREVENTERS are critical to the safety of the Crew, the Environment and the Rig, thus Blowout Preventers are intended to be Fail-Safe Devices. A good repair and maintenance of certified B.O.P.´s is the building block upon which Safety and Well Integrity are founded.

3 TIMELINE Argentinean Custom laws made very difficult to import used or rebuilt parts or tools for the oil industry (Including BOPs). Therefore, the BOPs that need to be exported to be repaired or certified cannot come back to the country; its allowed importing NEW preventers, but it was complicated for used or rebuilt parts. Industrias Petroleras del Sur (IPS) in Neuquen with Cameron license, was the single certified BOP repair workshop in Argentina and they were concentrated in the Drilling BOP segment. IPS had the infrastructure to repair/certify about 8 BOP´s a month. Most of them were Drilling BOP (11 & 13 5/8). Wenlen had the infrastructure to repair it´s own BOP´s as Manufacturer, but in the end of 90´s, the compañy dismantled the whole manufacture and repair line. Shaffer (BOP Manufacturer Company) tried to certify a repair shop, but did not achieve any Tech-Economics deal with any workshop in Argentina. INITIAL SITUATION 2006

4 TIMELINE INITIAL SITUATION: Importation complicated, One Overloaded Workshop, Homemade supplies. 2006

5 TIMELINE THE PROBLEM: The large number of preventers needed to be serviced, urged the contractors to hire improvised workshops and use not original or homemade spares to repair the equipment. There were several incidents in Workover and Pulling Rigs related to BOP´s failures. The situation generated a lack of confidence among operators. 2006 Late 2006 INITIAL SITUATION: Importation complicated, One Overloaded Workshop, Homemade supplies.

6 TIMELINE THE PROBLEM: Incidents regarding BOP´s failures, disappointed operators. 2006 Late 2006 INITIAL SITUATION: Importation complicated, One Overloaded Workshop, Homemade supplies.

7 TIMELINE THE REQUIREMENTS:. Pride International made a presentation at the 2007 Drilling Congress clearing up the situation with the BOP (Drilling, Workover & Pulling) and the urgency ofdeveloping certified workshops to address the problem. There were about 200 BOPs queuing to be repaired Only in WO & Pulling, the market demanded a minimum of 5 BOP repairs a month. IPS capacity was 2 to 2.5. 2006 Late 2006 2007 INITIAL SITUATION: Importation complicated, One Overloaded Workshop, Homemade supplies. THE PROBLEM: Incidents regarding BOP´s failures, disappointed operators.

8 TIMELINE THE REQUIREMENTS:. A New certified workshop is requiered. 2006 Late 2006 2007 INITIAL SITUATION: Importation complicated, One Overloaded Workshop, Homemade supplies. THE PROBLEM: Incidents regarding BOP´s failures, disappointed operators.

9 TIMELINE 2006 Late 2006 2007 Rig Activity Dropped Early 2008 INITIAL SITUATION: Importation complicated, One Overloaded Workshop, Homemade supplies. THE PROBLEM: Incidents regarding BOP´s failures, disappointed operators. THE REQUIREMENTS:. A New certified workshop is requiered.

10 TIMELINE 2006 Late 2006 2007 The situation worsened: In 2008 the oil industry activity dropped and reduced the IPS workload which conducted a reduction in the IPS staff and repair capacity. IPS reduced it capacity from 8 to 6 BOP´s per month, between annulars and rams. Early 2008 INITIAL SITUATION: Importation complicated, One Overloaded Workshop, Homemade supplies. THE PROBLEM: Incidents regarding BOP´s failures, disappointed operators. THE REQUIREMENTS:. A New certified workshop is requiered. Rig Activity Dropped

11 TIMELINE 2006 Late 2006 2007 Early 2008 INITIAL SITUATION: Importation compicated, One Overloaded Workshop, Homemade supplies. THE PROBLEM: Incidents regarding BOP´s failures, disappointed operators. THE REQUIREMENTS:. A New certified workshop is requiered. Rig Activity Dropped

12 TIMELINE THE PLAN:. The problem was addressed by LADS (Argentine Chapter) which appointed a technical committee The objectives were identified and a list of tasks was made 2006 Late 2006 2007 2008 Early 2008 INITIAL SITUATION: Importation complicated, One Overloaded Workshop, Homemade supplies. THE PROBLEM: Incidents regarding BOP´s failures, disappointed operators. THE REQUIREMENTS:. A New certified workshop is requiered. Rig Activity Dropped

13 The problem was addressed by LADS (Capitulo Argentina) which appointed a technical committee The objectives were identified and a list of tasks was made THE REQUIREMENTS:. A New certified workshop is requiered. THE PROBLEM: Incidents regarding BOP´s failures, disappointed operators. INITIAL SITUATION: Importation forbidden, One Overloaded Workshop, Homemade supplies. TIMELINE THE PLAN:. 2006 Late 2006 2007 2008 Early 2008 OBJECTIVES:. Critical Equipment 1.BOP Valves 2.Conection between BOP - Choke Manifold 3.Choke Manifold 4.Accumulators and BOP actuators. Planned Tasks: 1.Developed a BOP´s country inventory. 2.Develop of inspection and repair procedures. 3.Perform Handling, maintenance and field pressure test procedures. 4.Define documentation to provide traceability.. 5.Establish a list of suppliers that meet the requirements. 6.Help to develop new repair workshops.

14 TIMELINE THE PLAN:. Technical committee appointed, list of objectives. 2006 Late 2006 2007 2008 Early 2008 INITIAL SITUATION: Importation complicated, One Overloaded Workshop, Homemade supplies. THE PROBLEM: Incidents regarding BOP´s failures, disappointed operators. THE REQUIREMENTS:. A New certified workshop is requiered. Rig Activity Dropped

15 TIMELINE THE PLAN:. Technical committee designed, list of objectives. THE ACTIONS:. Perform a BOP´s inventory. Select Potencial workshops Help to develop the candidates to establish procedures, policies and standards. 2006 Late 2006 2007 2008 2009 Early 2008 INITIAL SITUATION: Importation complicated, One Overloaded Workshop, Homemade supplies. THE PROBLEM: Incidents regarding BOP´s failures, disappointed operators. THE REQUIREMENTS:. A New certified workshop is requiered. Rig Activity Dropped

16 THE INITIAL SITUATION: Importation forbidden, one workshop overcharged, homemade supplies. THE PROBLEM: Incidents regarding BOP´s malfunction, unconformity among operators. TIMELINE THE REQUIREMENTS:. Pride Presents the problem, new workshop is requiered. THE PLAN:. Technical committee designed, list of objectives. THE ACTIONS:. Perform a BOP´s inventory. Select Potencial suppliers candidates. Help to develop this candidates according policies and standards. There were near 500 B.O.P. units in Argentina Sort by Rig TypeSort by BrandSort by SizeSort by Pressure 135 units (32%) 282 units (68%) Annular Type A Ram Type R

17 TIMELINE THE INITIAL SITUATION: Importation forbidden, one workshop overcharged, homemade supplies. THE PROBLEM: Incidents regarding BOP´s malfunction, unconformity among operators. THE REQUIREMENTS:. Pride Presents the problem, new workshop is requiered. THE PLAN:. Technical committee designed, list of objectives. THE ACTIONS:. Perform a BOP´s inventory. Select Potencial suppliers candidates. Help to develop this candidates according policies and standards. Annular Type A Ram Type R There were near 500 B.O.P. units in Argentina Sort by Rig TypeSort by BrandSort by SizeSort by Pressure No Data 2006 Late 2006 2007 2008 2009

18 TIMELINE THE INITIAL SITUATION: Importation forbidden, one workshop overcharged, homemade supplies. THE PROBLEM: Incidents regarding BOP´s malfunction, unconformity among operators. THE REQUIREMENTS:. Pride Presents the problem, new workshop is requiered. THE PLAN:. Technical committee designed, list of objectives. THE ACTIONS:. Perform a BOP´s inventory. Select Potencial suppliers candidates. Help to develop this candidates according policies and standards. There were near 500 B.O.P. units in Argentina Sort by Rig TypeSort by BrandSort by SizeSort by Pressure Annular Type A Ram Type R No Data

19 TIMELINE THE INITIAL SITUATION: Importation forbidden, one workshop overcharged, homemade supplies. THE PROBLEM: Incidents regarding BOP´s malfunction, unconformity among operators. THE REQUIREMENTS:. Pride Presents the problem, new workshop is requiered. THE PLAN:. Technical committee designed, list of objectives. THE ACTIONS:. Perform a BOP´s inventory. Select Potencial suppliers candidates. Help to develop this candidates according policies and standards. There were near 500 B.O.P. units in Argentina Sort by Rig TypeSort by BrandSort by SizeSort by Pressure Annular Type A Ram Type R No Data 2006 Late 2006 2007 2008 2009

20 TIMELINE THE INITIAL SITUATION: Importation forbidden, one workshop overcharged, homemade supplies. THE PROBLEM: Incidents regarding BOP´s malfunction, unconformity among operators. THE REQUIREMENTS:. Pride Presents the problem, new workshop is requiered. THE PLAN:. Technical committee designed, list of objectives. THE ACTIONS:. Perform a BOP´s inventory. Select Potencial suppliers candidates. Help to develop this candidates according policies and standards. There were near 500 B.O.P. units in Argentina Sort by Rig TypeSort by BrandSort by SizeSort by Pressure Annular Type A Ram Type R No Data

21 TIMELINE THE PLAN:. Technical committee designed, list of objectives. THE ACTIONS:. 2006 Late 2006 2007 2008 2009 Early 2008 INITIAL SITUATION: Importation complicated, One Overloaded Workshop, Homemade supplies. THE PROBLEM: Incidents regarding BOP´s failures, disappointed operators. THE REQUIREMENTS:. A New certified workshop is requiered. Perform a BOP´s inventory. Select Potencial workshops Help to develop the candidates to Establish procedures, policies and standards. Rig Activity Dropped

22 TIMELINE THE INITIAL SITUATION: Importation forbidden, one workshop overcharged, homemade supplies. THE PROBLEM: Incidents regarding BOP´s malfunction, unconformity among operators. THE REQUIREMENTS:. Pride Presents the problem, new workshop is requiered. THE PLAN:. Technical committee designed, list of objectives. THE ACTIONS:. Perform a BOP´s inventory. Select Potencial suppliers candidates. Help to develop this candidates according policies and standards. THE SUPPLIER CANDIDATES Several workshop were selected. During a few meetings, the technical support was offered but also, the responsibility in case of some incident involving repaired equipment was explained too. After this stage only two suppliers continue with the process. ACYS, located in Mendoza city, and Wenlen that has the capacity to repair its own BOP´s also..

23 TIMELINE THE PLAN:. Technical committee designed, list of objectives. THE ACTIONS:. 2006 Late 2006 2007 2008 2009 Early 2008 INITIAL SITUATION: Importation complicated, One Overloaded Workshop, Homemade supplies. THE PROBLEM: Incidents regarding BOP´s failures, disappointed operators. THE REQUIREMENTS:. A New certified workshop is requiered. Perform a BOP´s inventory. Select Potencial workshops Help to develop the candidates to Establish procedures, policies and standards. Rig Activity Dropped

24 TIMELINE THE INITIAL SITUATION: Importation forbidden, one workshop overcharged, homemade supplies. THE PROBLEM: Incidents regarding BOP´s malfunction, unconformity among operators. THE REQUIREMENTS:. Pride Presents the problem, new workshop is requiered. THE PLAN:. Technical committee designed, list of objectives. THE ACTIONS:. Perform a BOP´s inventory. Select Potencial suppliers candidates. Help to develop this candidates according policies and standards. THE PROCEDURES Help the supplier with the repair procedures: disassembly, cleaning, sandblasting, dimensional and hardness analysis, assembly & testing, etc. The procedure was tested several times by committee members of and amended by the company, until the definitive procedure was reached. ACYS applied to Shaffer approval but they can´t achieved any Tech-Economics deal; hence, decided to apply to the ISO 9001-2000 certification, according to the requirements of API 16° Annex 8 and recommendations API RP 53, which managed to attain in June 2009.

25 TIMELINE THE PLAN:. Technical committee designed, list of objectives. THE ACTIONS:.BOP´s, candidates development. 2006 Late 2006 2007 2008 2009 Early 2008 INITIAL SITUATION: Importation complicated, One Overloaded Workshop, Homemade supplies. THE PROBLEM: Incidents regarding BOP´s failures, disappointed operators. THE REQUIREMENTS:. A New certified workshop is requiered. Rig Activity Dropped

26 TIMELINE 2006 Late 2006 2007 2008 2009 2012 THE PLAN:. Technical committee designed, list of objectives. THE ACTIONS:.BOP´s, candidates development. THE FINAL RESULT Early 2008 INITIAL SITUATION: Importation complicated, One Overloaded Workshop, Homemade supplies. THE PROBLEM: Incidents regarding BOP´s failures, disappointed operators. THE REQUIREMENTS:. A New certified workshop is requiered. Rig Activity Dropped

27 THE FINAL RESULT EVALUATION STAGE After arriving the BOP to the workshop a tag number is assigned and an evaluation check list is performed, involving the related tasks and responsibilities Tasks: Identification of every single piece and valve. Dimensional evaluation; Visual and not- destructive tests, hardness test, Nital. After the BOP is evaluated, the customer receives a budget and a detailed report including,photographic records of the parts to be replaced or repaired. THE REBUILDING PROCESS

28 THE FINAL RESULT EVALUATION STAGE THE REBUILDING PROCESS

29 THE FINAL RESULT REPAIR STAGE Once the client accepts the budget, the repair stage begins. This stage could include Welding filler, heat treatment, forged, etc. The policy of the shop is always to asks the client for new spare parts to repair the BOP THE REBUILDING PROCESS

30 THE FINAL RESULT REPAIR STAGE THE REBUILDING PROCESS

31 THE FINAL RESULT TEST STAGE After the repair is done, the equipment is ensembles and tested The tests are conducted with calibrated manometers and tools, hydraulic unit and a multiplier booster (able to bring the pressure up to 9000 psi.) THE REBUILDING PROCESS

32 THE FINAL RESULT TEST STAGE THE REBUILDING PROCESS

33 THE FINAL RESULT DELIVERY STAGE THE REBUILDING PROCESS

34 CONCLUSION In 2009 8 BOP´s were repaired and certificated. In 2010 23 BOP´s. In 2011 27 BOP´s. In 2012 42 BOP´s so far. The total BOP´s at ACYS as today: 98. THE REPAIR ACTIVITY OF ACYS CLIENTS: Nabors, Key Energy, Archer DLS, Ensign, ENAP (Chile) EMEPA, Skanska, Petroneu and SAI (Bolivia)

35 CONCLUSION Amount of BOP´s per year: Certifications RP-53/97…………………………..60 / 70 units Preventive maintenance in 5 year period……….20 /25 units Rebuilded Brands: Shaffer Hydril Cameron Rams40%10%50% Annulars20%70%10% The average rebuilding time is 90 days, since 2006 there were near 450 BOP´s repaired. THE REPAIR ACTIVITY OF IPS

36 CONCLUSION Rebuild In the last year no repairs were made. THE REPAIR ACTIVITY OF WENLEN YrClientBOP Quant ityObservations 2006PERBRAS7.1/16" 5000" Double Ram2Certified 16 A 2007OXY11" 3000# Double Ram2Certified 16 A 2008EMEPA7.1/16" 5000" Double Ram2Certified 16 A 2009CAPEX7.1/16" 5000# Single Ram1Certified 16 A 2009UTENEU7.1/16" 3000# Double Ram2Certified 16 A 2010SAN ANTONIO7.1/16" 5000" Double Ram1Certified 16 A 2010ROCH11" 3000# Double Ram1Certified 16 A 2010CAPEX7.1/16" 5000# Single Ram1Certified 16 A 2011SERVIPETROL13.5/8" 5000# Double Ram1Certified 16 A 2011APCO-UTE11" 3000# Double Ram1Certified 16 A 14

37 CONCLUSION MOST OF THE BOPS THAT ARRIVES TO THE SHOP ARE IN VERY POOR CONDITION. DAMAGES INCLUDE SHOCKS, CORROSION, EROSION, SCRATCHED SLEEVES & DAMAGES STUDS MOST OF THE DAMAGES ARE MADE BY MISHANDLING, POOR STORAGE CONDITIONS, LACK OF PREVENTIVE MAINTENANCE AND POOR TRAINED PERSONNEL THE VARIABLE THAT DETERMINES THE REPAIR TIME IS THE GENERAL CONDITION OF THE BOP AT ARRIVING. IMPROVING PREVENTIVE MAINTENANCE AND REINFORCING OPERATION PROCEDURES WILL HELP TO REDUCE THE REBUILDING AND CERTIFYING TIME. FACTS

38 ACKNOWLEDGMENT ACYS WENLEN IPS LADS ARGENTINA