Electronic Systems Support LHC LVPS Procurement - Status Reported by: Chris Parkman, PH-ESS February 10, 2006 Tests by: Bruno Allongue, Philippe Fontaine,

Similar presentations


Presentation on theme: "Electronic Systems Support LHC LVPS Procurement - Status Reported by: Chris Parkman, PH-ESS February 10, 2006 Tests by: Bruno Allongue, Philippe Fontaine,"— Presentation transcript:

1 Electronic Systems Support LHC LVPS Procurement - Status Reported by: Chris Parkman, PH-ESS February 10, 2006 Tests by: Bruno Allongue, Philippe Fontaine, Edgar Dos Santos (PH-ESS) Francis Anghinolfi (PH-MIC), Mark Beharrell (IT-CO) Georges Blanchot (PH-ATE), Alexander Singovski (CMS ECAL) Acknowledgements to: Federico Faccio (PH-MIC) László Ábel, Dante Gregorio (FI-PI)

2 2 10 Feb. '06 - cp PH-ESS LVPS Procurement Technical approval Wiener Approval given with reservations Magnetic field tolerance EC conformity OPC Server Procurement underway First release order issued CAEN Approval suspended Electrical conformity Environmental conformity EC conformity OPC Server Procurement started Accepting requests from experiments Technical reports in preparation

3 3 10 Feb. '06 - cp PH-ESS LVPS Procurement Wiener Electrical - approved Maraton, F8 & F12 CE conformity (Maraton will be tested by TÜV in March) Magnetic field tolerance 1100 Gauss rather than 1200 Bimetal thermal cut-out changed – to be tested Radiation tolerance - approved TID & SEE (spec: 140Gy over 10 years, 2*10 11 p/cm 2 ) October 2005 Uppsala proton tests showed no effects up to 5.03*10 10 p/cm 2 Probable failure of non-radiation tolerant AC/DC/PFC December 2005 PSI proton tests showed no effects up to 2*10 11 p/cm 2 NIEL (spec: n/cm 2 over 10 years) January 2005 Prospero neutron tests showed no effects up to ~6*10 12 n/cm 2 OPC server Qualified approval for the Maraton (monitoring only over Ethernet) Full F12 functionality over Ethernet (sample end March) Full functionality over Ethernet & CAN (sample two months after approval of F12)

4 4 10 Feb. '06 - cp PH-ESS LVPS Procurement ATLAS TRT, LHCb OPC Server Water cooled Spec A LHCb ATLAS-TRT 2. Control & monitoring 385VDC 230VAC, single phase 1. AC-DC (w. PFC) Ethernet 3. Maraton 12ch 50A DC-DC (3kW) High radiation & magnetic field tolerance μPμPμPμP

5 5 10 Feb. '06 - cp PH-ESS LVPS Procurement OPC Server ALICE 230VAC, single phase PL500-F12 12ch 50A DC-DC μPμP Ethernet ALICE Spec A Water cooled Low radiation & magnetic field tolerance

6 6 10 Feb. '06 - cp PH-ESS LVPS Procurement CMS ECAL CAN 230VAC, single phase PL500 6ch 100A DC-DC CMS-ECAL μPμP Radiation is present at a level below 4Gy and MeV equivalent neutrons/cm 2 over 10 years, of which approximately 10% are above 20MeV. Stray magnetic fields are present at a level up to 180mT. Spec B CMS OPC Server Water cooled Neutron radiation & high magnetic field tolerance

7 7 10 Feb. '06 - cp PH-ESS LVPS Procurement ATLAS Pixels 230VAC, single phase Ethernet ATLAS - Pixels Spec A OPC Server PL500-F12 12ch 50A DC-DC ATLAS Pixels μPμP Air cooled No radiation or magnetic field tolerance

8 8 10 Feb. '06 - cp PH-ESS LVPS Procurement CAEN EASY Electrical Out of spec Power factor EMC Efficiency Noise and ripple CE conformity Need approval by independent laboratory - auto-declaration is insufficient Magnetic field tolerance In spec Gauss Radiation tolerance Tests so far October (PH-ESS) – TSL Uppsala - proton tests showed TID effect and SEE December (PH-ESS) - PSI - proton tests identified particularly sensitive area on boards January (Atlas Muons/CAEN) - Casaccia - gamma tests showed TID effect January (Atlas Muons/CAEN) - TSL Uppsala - proton tests to refine diagnosis and test replacement components also tests of HV boards Planned tests February (PH-ESS) - Prospero - neutron tests end February (PH-ESS) February or March (ATLAS Muons/CAEN) - Pavia - gamma tests on test samples for TID effects March (PH-ESS/CAEN) - PSI - tests on sample boards to verify solution to SEE May (PH-ESS) - TSL Uppsala - final verification (repeat of October tests) OPC server Number of problems identified by IT-CO Solutions promised on March time-scale

9 9 10 Feb. '06 - cp PH-ESS LVPS Procurement CAEN – Electrical issues: actions Power factor The tender calls for a minimum Power Factor of 0.95 (since relaxed to 0.85) The measured value for the A3486 when delivering 3500W was 0.75 With the addition of the harmonic trap (passive filter) a Power Factor >0.9 was measured at 3500W output power and 0.7 at 1730W CAEN will tune the passive filter to cover a wider range of loads, and/or put the two channels in series (two notch filters) Mains harmonic rejection The A3486 was found to be non-conformant to the EN Specification at all loads, however with the addition of the mains filter, the conditions of EN were met at all loads. Use the passive filter (CAEN are not envisaging active power factor correction) Efficiency The specification calls for an overall efficiency (power out/power in) of better than 70% at loads from 10 to 100% of full load The A3486 and A3009 show overall efficiencies of less than 60% at all loads. The A3486 had an efficiency of 88% at an output of 3500W, the A % at maximum possible output (the nominal output was not attainable) - thus giving an overall efficiency of some 58%. PH-ESS showed the major losses to be apparently associated with the transformer (on the A3009). CAEN to investigate further Other parameters On the A3009 measured, the voltage turn-off (fall) was not to specification (5mS) and the current limit could not be tested since it was not possible to reach the nominal output current (~8.8A instead of 9A), also the over-voltage protection did not function as specified (apparently no crow- bar) CAEN are looking to a firmware solution

10 10 10 Feb. '06 - cp PH-ESS LVPS Procurement CAEN – Radiation tolerance: actions Six components identified as sources of problems Pulse width modulator - UCC3580 The UCC3580 will be replaced the non-pin compatible UC3525 (as used successfully in Casaccia and Uppsala on an ATLAS HV board) New versions of the aux DC/DC (CAEN code: DC5) and of the drivers (CAEN code: DRIVXA and DRIVXC) in preparation MOS driver TC4427 – transformer input driver Replacement being proposed (LM5111 or TC4424), has apparently performed well (tests in Uppsala, Week 4) EEPROM - control circuits Pin compatible replacement being proposed. 6 x Schmitt-trigger inverter 74HC14 – general use Components from Fairchild seem particularly sensitive – change to other maker Operational amplifier LM393 used as a comparator Remove completely – redundant monitoring function Opto-couplers HPL0630 – SEEs inducing spurious resets to the microprocessor controller Implement a low-pass filter on the reset line to reduce spikes, demonstrated during tests in Uppsala, Week 4

11 11 10 Feb. '06 - cp PH-ESS LVPS Procurement CAEN – OPC server Hardware persistency (§5.3) Error states in the CAEN HW did not persist across power cycling the HW. Voltage set point not preserved (§5.4) Under investigation – waiting for new OPC Server release. Fault tolerance (§5.5.2) A specific start-up sequence results in incorrect OPC quality values for some of the items. CAEN to retest. Data (Device) Source Access (§5.5.3) The OPC server reads from a cache in the 1527 rather than the Easy modules. Human readable configuration file (§5.5.4) IT-CO to check again. Stability & performance (§5.5.5) Random server crashing. Work in progress Diagnostic Facilities (§5.5.6) Requires a new release of the OPC server. IT-CO (Mark Beharrell) is waiting for the next OPC server release before continuing his tests. Provisional schedule – end-February.

12 12 10 Feb. '06 - cp PH-ESS LVPS Procurement 400VAC, 3-phase CAEN LVPS layout 48VDC 1ch 100A DC-DC 2ch 50A DC-DC 4ch 25A DC-DC 6ch 16A DC-DC 12ch 9A DC-DC 400VAC, 3-phase Filter AC-DC μPμPμPμPμPμP 48V Service EASY crate (w. crate controller) ALICE - TOF LHCb - VELO ATLAS - Muons CMS Ethernet OPC Server Control & monitoring μPμP Spec A Spec B

13 13 10 Feb. '06 - cp PH-ESS LVPS Procurement Procurement Status First Wiener release order being processed (~2.7MCHF)Wiener release order Second release order in preparation Requests accepted for first CAEN release order Schedule Wiener Wiener will inform us of their production possibilities - next week Faced with large orders for LVPS and crates Any prioritisation between individual orders will be made by users with PH-ESS Deliveries likely to be late summer… CAEN Long lead-time components ordered against informal notification of requirements Despite delay in approval, ordering may proceed, but no payment before technical acceptance Prioritisation difficult given large quantities ordered outside CERN contract Deliveries likely to be late summer…

14 14 10 Feb. '06 - cp PH-ESS LVPS Procurement PH-ESS request form Please use the PH-ESS request form whenever possible Allows request to be tracked For specials Catalogue Existing requests with status Add items

15 Electronic Systems Support Changes, Options, Parts

16 16 10 Feb. '06 - cp PH-ESS LVPS Procurement Wiener - changes Inclusion of OPC server licence in price – no separate licence All monolithic power supplies Maraton control and monitoring module RCM 0R > 0R Crate for 6 Primary Rectifier Modules 0B > 0B addition of screw terminal block at rear

17 17 10 Feb. '06 - cp PH-ESS LVPS Procurement Wiener parts in CERN Stores Amphenol connector for 385VDC input to Maraton power converter Thanks to Vincent Bobillier & Georges Blanchot

18 18 10 Feb. '06 - cp PH-ESS LVPS Procurement Suggested cables for Wiener Maraton Cable for 385VDC Primary Rectifier to Maraton Cable for RCM to Maraton

19 19 10 Feb. '06 - cp PH-ESS LVPS Procurement Wiener Options 1: over-voltage protection CMS ECAL A never-exceed output voltage achieved by the use of a non-linear transformer ALICE Limits the voltage at the end of the sense line (detector end) to a user defined value This value is fixed at factory and cannot be adjusted by the user A pure hardware limitation independent of the channel processor

20 20 10 Feb. '06 - cp PH-ESS LVPS Procurement Wiener Options 2: CERN patch-panel Approximate cost mounted on the 0B power bin with connections to the Wiener rear-panel – 250 CHF Customised paralleling, etc., possible - needs care (possibility of damage …) Screens connected by clamping-bar in rack Consider whether you would like the power bin delivered early to allow rack installations to proceed Right-angled lugs available from the CERN Stores More on lugs

21 21 10 Feb. '06 - cp PH-ESS LVPS Procurement Right-angled lugs

22 22 10 Feb. '06 - cp PH-ESS LVPS Procurement CAEN Options: Anderson Connectors v. Screw Terminals A channelsA channels Screw terminals preferred

23 Electronic Systems Support Electrical & Environmental Tests

24 Electronic Systems Support Wiener Electrical tests

25 25 10 Feb. '06 - cp PH-ESS LVPS Procurement Wiener PL500 F12 electrical tests - overview Static regulation: Spec: 0.5% Test: 0.026%. Dynamic regulation: Spec: 10% of set voltage Test: 1% Efficiency: Spec: >70% Test: 72% Power factor Spec: 0.95 Test: Noise and ripple: Spec: < 10mV at output terminals Test: ~30mv p/p at 200MHz Test: ~13mv p/p at 20MHz Turn ON time: Spec: >50ms, <100ms Test: 80ms. Turn OFF time: Spec: <5ms Test: 90ms EMC EN compliant 230VAC, single phase OPC Server PL500-F12 12ch 50A DC-DC ATLAS Pixels 0M Monolithic 3U 19" power box, 230V 50Hz PFC input, 12 channel DC output, 2-8V, 90W nominal, 11.5A max, 10A continuous, Ethernet control. OPC server licence. Ethernet In discussion with Wiener

26 26 10 Feb. '06 - cp PH-ESS LVPS Procurement Wiener Maraton electrical tests - overview Static regulation: Spec: 0.5% Test: 0.034%. Dynamic regulation: Spec: 10% of set voltage Test: 8%. Efficiency: Spec: >70% Test: 75.2% Power factor Spec: 0.95 Test: (full load) Test: (one channel, full load) Noise and ripple: Spec: < 10mV at output terminals Test: 15mv p/p at 200MHz - 8mv p/p at 20MHz Turn ON time: Spec: >50ms, <100ms Test: 75ms. Turn OFF time: Spec: <5ms Test: 2.5ms. Current limit protection: Spec: 110% of rated current Test: 55.4A adjustable Over voltage protection: Spec: 125% of set voltage Test: 6.2V EMC EN compliant 2. Control & monitoring 385VDC 230VAC, single phase 1. AC-DC (w. PFC) Ethernet 3. Maraton 12ch 50A DC-DC (3kW) 0M U 19" power box, 385VDC input, 12 channel DC output, 2-8V, 300W nominal, 55A max, 50A continuous, analogue controlled interface. Water cooled, no magnetic screening.

27 Electronic Systems Support Wiener radiation tests

28 28 10 Feb. '06 - cp PH-ESS LVPS Procurement Wiener Maraton – Uppsala October 2005 Spec. 2*10 11 p/cm p/cm 2 Probable cause – irradiation of the AC/DC/PFC module (non-radiation tolerant)

29 29 10 Feb. '06 - cp PH-ESS LVPS Procurement Wiener Maraton – PSI December 2005 Spec. 2*10 11 p/cm p/cm 2

30 Electronic Systems Support CAEN Electrical

31 31 10 Feb. '06 - cp PH-ESS LVPS Procurement CAEN A3486/A3009/A3025 electrical tests - overview EMC (conditions: loaded to 1728W - 36A, 48V) Non compliant with h5, h7, h11, h13, h17, h19 Power Factor 0.74 (spec. 0.95) The system exhibited non negligible level of common mode noise The environment was not optimum (no LISN, no ground plane). Static regulation Spec: 0.5% Test: < 0.5% of set voltage Dynamic regulation: Spec: 10% of set voltage Test: <10% of set voltage Efficiency Spec: >70%, % load Test: overall system 57% + loss in DC cable. AC/DC converter (A3486): 88%. DC/DC converter (A3009, A3025…): 65%. Noise and ripple: Need additional measurements (30m of cable with loads capacitance of 300uF) Turn on OK. Turn off > 5ms. Current limit protection: <110% of rated maximum current. Impossible to reach the nominal value. Overvoltage protection: In case of overvoltage, error message OVV on SY2527 screen but no drop of output voltage. No crowbar

32 Electronic Systems Support CAEN Radiation Tests

33 33 10 Feb. '06 - cp PH-ESS LVPS Procurement p/cm 2 CAEN A Uppsala October 2005

34 34 10 Feb. '06 - cp PH-ESS LVPS Procurement CAEN A Uppsala October 2005

35 35 10 Feb. '06 - cp PH-ESS LVPS Procurement CAEN A Uppsala October 2005

36 36 10 Feb. '06 - cp PH-ESS LVPS Procurement CAEN A Uppsala October 2005

37 37 10 Feb. '06 - cp PH-ESS LVPS Procurement p/cm 2 CAEN A Uppsala October 2005

38 38 10 Feb. '06 - cp PH-ESS LVPS Procurement CAEN A Uppsala October 2005

39 39 10 Feb. '06 - cp PH-ESS LVPS Procurement CAEN A Uppsala October p/cm 2 Restart beam p/cm 2

40 40 10 Feb. '06 - cp PH-ESS LVPS Procurement CAEN A PSI December 2005 A B C D E Input diode Switching transistor ? Power solid state fuse + microprocessor Service solid state fuse + EEPROM

41 41 10 Feb. '06 - cp PH-ESS LVPS Procurement PSI December 2005 CAEN A Area A: Ch. 2 Vout A

42 42 10 Feb. '06 - cp PH-ESS LVPS Procurement PSI December 2005 CAEN A Area A: input power current A

43 43 10 Feb. '06 - cp PH-ESS LVPS Procurement PSI December 2005 CAEN A Area A: input service current A

44 44 10 Feb. '06 - cp PH-ESS LVPS Procurement PSI December 2005 CAEN A Area D: communication D

45 45 10 Feb. '06 - cp PH-ESS LVPS Procurement PSI December 2005 CAEN A Area E: communication E

46 46 10 Feb. '06 - cp PH-ESS LVPS Procurement PSI December 2005 CAEN A Area A: Ch. 1 Vout A

47 47 10 Feb. '06 - cp PH-ESS LVPS Procurement PSI December 2005 CAEN A Area A: input power current A

48 48 10 Feb. '06 - cp PH-ESS LVPS Procurement PSI December 2005 CAEN A Area A: input service current A

49 49 10 Feb. '06 - cp PH-ESS LVPS Procurement PSI December 2005 CAEN A Area B: Ch. 1 Vout B

50 50 10 Feb. '06 - cp PH-ESS LVPS Procurement PSI December 2005 CAEN A Area B: input service current B

51 51 10 Feb. '06 - cp PH-ESS LVPS Procurement PSI December 2005 CAEN A Area B: input power current B

52 52 10 Feb. '06 - cp PH-ESS LVPS Procurement PSI December 2005 CAEN A Area C: Ch. 1 Vout C

53 53 10 Feb. '06 - cp PH-ESS LVPS Procurement PSI December 2005 CAEN A Area C: input power current C

54 54 10 Feb. '06 - cp PH-ESS LVPS Procurement PSI December 2005 CAEN A Area C: input service current C

55 55 10 Feb. '06 - cp PH-ESS LVPS Procurement PSI December 2005 CAEN A Area D: Ch.1 Vout D

56 56 10 Feb. '06 - cp PH-ESS LVPS Procurement PSI December 2005 CAEN A Area D: input power current D

57 57 10 Feb. '06 - cp PH-ESS LVPS Procurement PSI December 2005 CAEN A Area D: input service current D

58 58 10 Feb. '06 - cp PH-ESS LVPS Procurement PSI December 2005 CAEN A Area E: Ch.1 Vout E

59 59 10 Feb. '06 - cp PH-ESS LVPS Procurement PSI December 2005 CAEN A Area E: input power current E

60 60 10 Feb. '06 - cp PH-ESS LVPS Procurement PSI December 2005 CAEN A Area E: input service current E