Presentation is loading. Please wait.

Presentation is loading. Please wait.

SCHEDULE Nov 1st - Assembly Table Complete

Similar presentations


Presentation on theme: "SCHEDULE Nov 1st - Assembly Table Complete"— Presentation transcript:

1 SCHEDULE Nov 1st - Assembly Table Complete
Dec Larg Week - Initiate discussions with TIS…….. Meeting arranged with A. Merlino Jan 1st - Rotator Design Complete THIS WILL SLIP !! Jan 1st - Module Trolley Design - OKAY Feb 1st - Support Structure Design Probably an unrealistic date but additional manpower should be available at U-Vic. Feb 19/20 - Final Design Review ???? Mar 1st - Bid document ready ? This will be very difficult to meet ! Apr 15th - Place contract…… ???? Oct 15th - Ship to CERN Still a viable date. Nov 15th - Tooling arrives at CERN DECEMBER LARG WEEK 2000


Download ppt "SCHEDULE Nov 1st - Assembly Table Complete"

Similar presentations


Ads by Google