TRADE CONTACT GROUP Brussels 9th June Agenda item 3a) State of play of IT systems: Import Control System (ICS); Export Control System (ECS); New Computerized Transit System (NCTS); Economic Operators Systems (EOS). 09/06/2009 Trade Contact Group
2
ECG subgroup on ICS Title of presentation Subtitle 09/06/2009
Trade Contact Group
3
Centrally Developed Customs Applications and specifications
Central applications are developed and delivered according to the schedule Technical specifications are maintained/ changes are kept at minimum 09/06/2009 Trade Contact Group
4
Functional developments
Amendments of ENS after international diversion Declaring offices of subsequent entry in ENS 09/06/2009 Trade Contact Group
5
ICS Phase 1 National Plans 25/05/2009
availability trader specs start date operations DK 1/06/2009 1/09/2010 UK 12/03/2009 26/03/2010 PL 30/06/2009 1/03/2010 IT 3/03/2009 DE 6/02/2009 31/01/2010 IE 30/09/2008 1/01/2010 LT 22/12/2008 31/12/2009 CY 30/11/2008 EL 31/07/2008 NL 31/01/2009 4/12/2009 BG 1/07/2009 1/12/2009 SI LU 1/01/2009 FI 10/10/2008 24/11/2009 SE 15/12/2008 7/11/2009 FR 15/09/2008 26/10/2009 HU 30/01/2009 1/10/2009 BE 1/10/2008 RO 28/05/2009 LV 5/02/2009 CZ 20/10/2008 AT 31/08/2008 ES 1/07/2008 MT 1/08/2008 PT EE 1/12/2008 SK ICS Phase 1 National Plans 25/05/2009 09/06/2009 Trade Contact Group
6
ICS Phase 1 Conformance Test 06/06/2009
AT - Austria CT DONE BE - Belgium BG - Bulgaria CY - Cyprus CZ - Czech Republic CT < 99 % DE - Germany DK - Denmark EE - Estonia EL - Greece ES - Spain FI - Finland FR - France HU - Hungary IE - Ireland IT - Italy LT - Lithuania LU - Luxembourg LV - Latvia MT - Malta NL - The Netherlands PL - Poland PT - Portugal RO - Romania SE - Sweden SI - Slovenia CT < 25 % SK - Slovakia UK - The United Kingdom ICS Phase 1 Conformance Test 06/06/2009 09/06/2009 Trade Contact Group
7
ICS Phase 1 National plans and Conformance tests Summary
The Conformance tests started in 9 MS. SK, MT, AT, ES and PT finalised the CT The following MS announced commencement of operations beyond the deadline: DK, UK, DE, PL, IT, IE, CY, EL, BG, RO, NL, LU, FI, FR, HU, SE, LT, SI, BE The provisions in the Business Continuity Plan will ensure that the safety and security of goods entering the EU will be guaranteed. 09/06/2009 Trade Contact Group
8
ECG subgroup on ECS Directorate General Taxation and Customs Union Directorate Programme Management Unit A3 Customs Trans European Systems 09/06/2009 Trade Contact Group
9
Development, Conformance Testing and Operations
Development of Commission applications is finished Currently 23 MS have started their Conformance Testing campaigns. ES, FR, RO, IT finalised the CT Following Member States announced start of operations beyond the deadline: LU, DK, PL. 09/06/2009 Trade Contact Group
10
ECS Phase 2 Consolidated NPP 25/05/2009
NA availability trader specs start date operations LU 15/03/2009 4/01/2010 IT 20/03/2009 1/07/2009 DK 6/02/2009 26/09/2009 PL 16/02/2009 1/09/2009 EL 6/07/2009 CY 31/03/2009 IE 4/07/2008 UK 31/10/2008 BE 4/03/2009 CZ 10/12/2008 BG 24/03/2009 HU 15/12/2008 FI AT 31/08/2008 PT 28/10/2008 SI 25/01/2009 NL 31/12/2008 MT not applicable (only DTI) LV 30/01/2009 LT SK 30/09/2008 EE 25/02/2009 DE 28/03/2008 RO 12/09/2008 SE 9/12/2008 30/06/2009 ES 5/05/2009 FR 27/06/2008 ECS Phase 2 Consolidated NPP 25/05/2009 09/06/2009 Trade Contact Group
11
ECS Phase 2 Conformance test 06/06/2009
AT - Austria + CT < 75 % BE - Belgium BG - Bulgaria CY - Cyprus + CT < 99 % CZ - Czech Republic DE - Germany + CT < 50 % DK - Denmark EE - Estonia EL - Greece ES - Spain CT DONE FI - Finland FR - France HU - Hungary IE - Ireland + CT < 25 % IT - Italy LT - Lithuania LU - Luxembourg LV - Latvia MT - Malta NL - The Netherlands PL - Poland PT - Portugal RO - Romania SE - Sweden SI - Slovenia SK - Slovakia UK - The United Kingdom ECS Phase 2 Conformance test 06/06/2009 09/06/2009 Trade Contact Group
12
ECS Statistics 09/06/2009 Trade Contact Group
13
ECG subgroup on NCTS Title of presentation Subtitle 09/06/2009
Trade Contact Group
14
Development, Conformance Testing and Operations
Development of Commission applications is finished Conformance Testing started early November 2008 with NO Currently 28 NAs have started their Conformance Testing campaigns. CZ, SI, SK, CH finalised the CT. DE finalised the CT for safety and security. 09/06/2009 Trade Contact Group
15
NCTS Phase 4 Consolidated NPP 25/05/2009
NA start operations security start operations enquiry IT 1/07/2009 EL 6/07/2009 DE RO BE CY FR LT LU BG UK EE LV NL /07/2009 FI PT SI DK MT SK AT HU PL SE IE CZ ES 25/06/2009 NCTS Phase 4 Consolidated NPP 25/05/2009 NA start operations security start operations enquiry NO 1/07/2009 IS 1/07/2009 CH / FL AD SM 09/06/2009 Trade Contact Group
16
NCTS Phase 4 Conformance test 06/06/2009
AT - Austria = CT < 75 % BE - Belgium + CT < 50 % BG - Bulgaria CT < 99 % CY - Cyprus CZ - Czech Republic CT DONE DE - Germany DK - Denmark EE - Estonia + CT < 75 % EL - Greece + CT < 99 % ES - Spain FI - Finland FR - France HU - Hungary IE - Ireland + CT < 25 % IT - Italy LT - Lithuania LU - Luxembourg LV - Latvia MT - Malta NL - The Netherlands PL - Poland PT - Portugal RO - Romania SE - Sweden SI - Slovenia SK - Slovakia UK - The United Kingdom NCTS Phase 4 Conformance test 06/06/2009 AD - Andorra SM - San Marino CH - Switzerland CT DONE NO - Norway CT < 99 % 09/06/2009 Trade Contact Group
17
NCTS Statistics 09/06/2009 Trade Contact Group
18
ECG subgroup on EOS Title of presentation Subtitle 09/06/2009
Trade Contact Group
19
EOS Status on 25/05/2009 AEO Phase 1 running smoothly and data have been successfully migrated to EOS on without disruption of operations Since the start the number of applications is 2703 and the number of issued certificates is 1073. 09/06/2009 Trade Contact Group
20
Upload of the data in the system
EOS Status on 25/05/2009 EOS (joint EORI-AEO) central application is ready and available to the MSs on 07/4/2009 for: Conformance testing Upload of the data in the system Test of on-line EORI consultation by MS Since the migration from AEO Phase 1, on , the number of applications treated is 388 and the number of certificates issued is 213 EOS Conformance testing for Member States started according to the planning 09/06/2009 Trade Contact Group
21
EOS Conformance test 03/06/2009
AT - Austria CT < 25 % BE - Belgium + CT < 25 % BG - Bulgaria CY - Cyprus CT DONE CZ - Czech Republic DE - Germany DK - Denmark EE - Estonia EL - Greece ES - Spain FI - Finland FR - France HU - Hungary IE - Ireland IT - Italy LT - Lithuania LU - Luxembourg LV - Latvia + CT < 50 % MT - Malta NL - The Netherlands + CT < 75 % PL - Poland PT - Portugal RO - Romania SE - Sweden + CT < 99 % SI - Slovenia SK - Slovakia UK - The United Kingdom CT < 50 % EOS Conformance test 03/06/2009 09/06/2009 Trade Contact Group
22
EORI start-up data All Member States except AT; DE and PT have passed successfully the test scenario for the EORI start-up upload All Member States except AT; DE; IT and PT have stored the national EORI start-up file on the Commission server The national EORI start-up files are being loaded into the central EOS database. DE announced that they will not be able to meet the deadline, so DE data will be missing on AT started collecting EORI data on 3rd June. AT data will be missing on 01/ The consolidated EORI start-up data will be ready to be sent offline to the Member States on 11th June 2009 09/06/2009 Trade Contact Group
23
Conclusions For all safety and security related IT systems, the systems specifications are accepted and the central services software has been developed and tested Currently for all systems Conformance tests are ongoing Some Member States have encountered delays, especially in the case of ICS and will not meet the legal deadline of Based upon this information received from the MS on delays encountered, the Conformance test will have to continue after July 2009 until mid 2010 09/06/2009 Trade Contact Group