Presentation is loading. Please wait.

Presentation is loading. Please wait.

12 GeV Project Status Glenn R. Young 12 GeV Project Status

Similar presentations


Presentation on theme: "12 GeV Project Status Glenn R. Young 12 GeV Project Status"— Presentation transcript:

1 12 GeV Project Status Glenn R. Young 12 GeV Project Status
CLAS Collaboration Meeting Jefferson Lab June 14, 2017

2 Enhanced capabilities
12 GeV Upgrade Project Completion of the 12 GeV CEBAF Upgrade was ranked the highest priority in the NSAC Long Range Plan. Upgrade is designed to build on existing facility: vast majority of accelerator and experimental equipment have continued use. New Hall Add arc Enhanced capabilities in existing Halls Add 5 cryomodules 20 cryomodules Upgrade arc magnets and supplies CHL upgrade TPC = $338M ETC = $1.1M Project Scope (~99.7% complete) Doubling the accelerator beam energy - DONE New experimental Hall D and beam line - DONE Civil construction including Utilities - DONE Upgrades to Experimental Hall C - DONE Upgrades to Experimental Hall B - ~99.0% Maintain capability to deliver lower pass beam energies: 2.2, 4.4, 6.6….

3 Physics Progress Overall
Detectors and Electronics - Complete DAQ/Computing (software/firmware) - Complete Beamline - Complete Infrastructure - 99% Hall C, D - Complete Hall B - Install Solenoid magnet Magnets – 99% Hall C, D – Complete Hall B Torus – Complete Hall B Solenoid – 93% KPP Runs – 100%

4 DOE OPA Review May 10-11, 2017 Major “annual” review of 12 GeV Project
From the Report of the Review: The Installation of all detectors and detector subsystems is complete. Satisfactory operation of all detectors in Halls B, C, and D is confirmed. All CD-4b Key Performance Parameters (KPPs) are complete. Installation, cool-down, and power-up of all magnets in Halls B, C, and D, with the exception of the Hall B solenoid magnet, is complete. All delivered magnets are operating satisfactorily. The Hall B solenoid magnet assembly is continuing at the vendor site. The project team completed all activities necessary to support installation, cool-down, and power-up of the Hall B solenoid magnet when it arrives from the vendor. However, continued schedule delays with the solenoid magnet vendor have affected schedule contingency to the point that project completion by September 30, 2017 remains uncertain.

5 Solenoid Magnet Progress (as of 3/29/17)
All Coils Wound, Potted, Assembled, Merged into One Cold Mass Coils Spliced & Instrumented, Radiation Screens and MLI Ready One Major Step Remains: Suspend Cold Mass in Cryostat, Perform Closure Welding Delivery to JLab sets schedule for Project completion September 29, 2016 November 1, 2016 When I last addressed you

6 Transfer of Cold Mass Load to OVC
The transfer of the cold mass weight from the assembly tooling to the OVC is a critical step in the final assembly process. This task involves metrology, welding, mechanical assembly and instrumentation control to monitor the loading. Suspension Pocket and Radial Link Cold Mass Support Cradle for Cryostat Solenoid Suspension System Shield Coil Bobbin OVC Pocket Cryostat There are eight radial links supporting the cold mass assembly (4 shown here with another 4 on the other end) The installation of the radial support links is a complex process that requires the 15+ ton cold mass to be positioned to a radial and axial tolerance of <0.125”

7 Solenoid Suspension Parts
Solenoid Suspension System OVC Pocket Shield Coil bobbin Pocket Installed suspension Cold Mass with 2 Suspensions Visible S2 Glass Strap 1 of 2 Clevis Eye Steel Link with 2 roll pins

8 Faulty Clevis Eye Correctly Manufactured Clevis Eye is a Single Solid Piece Thin weld bead, perhaps 0.030” Faulty clevis eye was manufactured from two pieces welded together with the weld in this location. Bellows was attached to clevis eye and pocket, thus weld was hidden inside Bellows and therefore not visible during the quality inspection carried out by ETI. Rod Separated from Clevis Head Separated Clevis Head, Weld Bead Visible

9 New Clevis Eyes and Bellows
Solid Inconel Bar Stock for New Clevis Eyes Various Machining Stages Finished Solid Clevis Eye with New Bellows Photos by JLab Staff Member who Observed the Work

10 Successful Transfer to Suspension 4/19/17

11 Final Assembly The final steps in the solenoid assembly process include the installation of the face, conical and inner bore sections of the Radiation Shield, MLI and OVC components. Portions of the radiation shield and OVC are pre-assembled to improve efficiency of final assembly. The OVC welding is labor intensive due to the pressure vessel requirements and little space between the OVC and cold mass assemblies.

12 Radiation Shield (Re-)Installed 6/1/17

13 MultiLayer Insulation Installed 6/9/17

14 Outer Vacuum Cryostat Ends Installed 6/12/17

15 OVC Welding Started 6/13/17

16 ETI Completion Schedule
Terminate instrumentation feedthrough connectors (June 16) Weld Cryostat Endplate, Cone, Bore Sections to Central Shell (June ) MAGNET ASSEMBLY IS COMPLETE Load onto Shipping Frame (June ) Ship (June 27)

17 Solenoid Infrastructure at JLab
Solenoid Service Tower & U-tubes – Complete Solenoid I&C Construction – Complete Solenoid Hall B Infrastructure – Complete Shipping fixture / shipping contract - Complete / in place U-tube SST Installed Instrumentation and Controls Installed Solenoid Stand He Vaporizer Magnet Power Supply Solenoid Shipping Frame

18 Work at JLab after Solenoid Arrival
Arrival Checks Receiving inspection (vacuum, electrical, instrument), place on stand Remove shipping restraints, survey Cryogenics SST Attachment Place SST, splice power leads, complete piping, add radiation shield and MLI, weld SST cryostat bottom plate to solenoid, add lower thermal shield plate, attach vacuum pumping system I&C Attachment/Setup Add final internal sensors to SST, hook up all cables, hook up main Magnet Power Supply, test all I&C items Cryogenic Operation Setup Leak / Pressure / Reverse Leak checks, add U-tubes, circulate Helium Pump-down Cool-down Power test

19 Key Activities: Path to CD-4B
Level 2 Milestones (PEP) Number  Milestone Description  Baseline  Projected  Actual Status 2-12 Hall D Equipment Installation Completed Sep-14 Oct-14 CD-4B 2-13 Hall D Beam Commissioning Completed Dec-14 2-27 Hall C Q1 Magnet Delivered Jan-15  2-28 Hall C HB Magnet Delivered Mar-15 2-34 Hall B Torus Cold Mass Delivered Apr-15 2-38 Conventional Facilities Complete Dec-15 Nov-15 2-29 Hall C Dipole Magnet Delivered Nov-16 2-30 Hall C Q2 Magnet Delivered Oct-16  2-31 Hall C Q3 Magnet Delivered Mar-16 Nov-16  2-35 Hall B Solenoid Cryostated Coil Delivered June-17 2-32 Hall C Equipment Installation Complete Jul-16 Feb-17  2-33 Hall C Beam Commissioning Complete Aug-16 Mar-17  2-36 Hall B Equipment Installation Complete Oct-16 Sept-17 2-37 Hall B Beam Commissioning Complete Dec-16

20 Summary All 12 GeV Project Scope is complete except Solenoid
ETI is welding the cryostat – the LAST step before shipping Solenoid expected to ship June 27 JLab has prepared all infrastructure for the Solenoid and is ready to receive and install it Plans for commissioning (pump-down, cool-down, and power-up) are prepared for Physics Division ERRs Plan to complete Solenoid Commissioning by September 30


Download ppt "12 GeV Project Status Glenn R. Young 12 GeV Project Status"

Similar presentations


Ads by Google