Cost and schedule for ELENA Beam Transfer Systems W. Bartmann, J. Borburgh, E. Carlier, L. Ducimetiere, T. Fowler, M. Hourican, R. Ostojic, L. Sermeus.

Similar presentations


Presentation on theme: "Cost and schedule for ELENA Beam Transfer Systems W. Bartmann, J. Borburgh, E. Carlier, L. Ducimetiere, T. Fowler, M. Hourican, R. Ostojic, L. Sermeus."— Presentation transcript:

1 Cost and schedule for ELENA Beam Transfer Systems W. Bartmann, J. Borburgh, E. Carlier, L. Ducimetiere, T. Fowler, M. Hourican, R. Ostojic, L. Sermeus ELENA Cost and Schedule Review, 21 st November 2014

2 Outline Overview AD kickers platform removal Elena injection kicker – Electromechanical HW – HV generators Injection Septum Ion switch Fast Deflectors Quadrupole assembly Electrostatic deflectors 21/11/2014Cost&Schedule ELENA Beam Transfer2

3 Overview 21/11/2014Cost&Schedule ELENA Beam Transfer3

4 Element overview Length of electrostatic lines: 95 m – 31.5 m not included in initial cost estimate (Source-, BASE-, ASACUSA2 line) Injection: – 1 magnetic septum, 1 magnetic kicker Extraction: – 2 fast pulsed electric deflectors Source injection: – Electrostatic ion switch – Polarity reversal on line and injection equipment required Transfer lines: – 64 quadrupole assemblies (focussing and steering) – 7 fast pulsed electric deflectors – 10 electrostatic bends 21/11/2014Cost&Schedule ELENA Beam Transfer4

5 AD kickers platform removal HV generators removal – 600 kCHF – 10/13 – 05/15 – Platform removal (“point of no return”): 12/14 – 76 kCHF transferred to AD consolidation (WU129511) for AD Main and Dump switch rejuvenation – Overspend on transmission cables (2x estimate due to first prototype out of spec and half price paid, reviewed design more expensive) and connectors – Transmission cable delivery (1km) not guaranteed for end 03/15 – Decision if existing cables are removed for recuperation or not by 02/15 Displace electronics – 550 kCHF – 01/14 - 03/16 21/11/2014Cost&Schedule ELENA Beam Transfer5

6 AD kickers platform removal 21/11/2014Cost&Schedule ELENA Beam Transfer6 sub-WP 2: AD kickers HV generators platform removal Person in charge:Luc Sermeus Budget of WU (kCHF):598 Work Unit WU Start dateFinish dateAdvancementBudget Person reporting(dd/mm/yy) (% of total sub-WU)2014201520162017 Perform infrastructure design B393Luc Sermeus18/10/1331/01/140%2 Install new infrastructure in B393Luc Sermeus21/03/1403/04/1421%124 Etudes modifications MS&DSLuc Sermeus15/08/1431/12/143%15 Installation of 2dump switchesLuc Sermeus01/07/1431/01/151% 4 Installation of 2 main switchesLuc Sermeus01/08/1431/01/151% 4 Installation of 6 dump switchesLuc Sermeus01/10/1428/02/153%123 Connect 2 PFLs to switchesLuc Sermeus01/01/1528/02/150%2 Transmission cables spec., order & delivery (500m proto) Luc Sermeus01/12/1315/05/143%16 Tx cable connector studyLuc Sermeus01/02/1431/08/143%19 Transmission cables order & delivery (500m)Luc Sermeus01/07/1430/11/146%38 Transmission cables order & delivery (1000m)Luc Sermeus01/07/1430/03/1513% 75 Removal of generators and platform from B193Luc Sermeus15/12/1428/02/152% 10 Cable removalLuc Sermeus01/01/1501/04/152% 10 Installation of 6 main switchesLuc Sermeus31/01/1515/02/152% 12 Connect 6 PFLs to switchesLuc Sermeus16/02/1531/03/150%2 Oil system installationLuc Sermeus01/09/1431/03/1529%60115 SF6 piping workLuc Sermeus01/02/1531/03/153%315 Transmission cables pullingLuc Sermeus01/03/1530/04/152% 10 Tx cable connectors (2x19)Luc Sermeus01/04/1515/05/156% 38 Commissioning of 8 AD generatorsLuc Sermeus06/04/1531/05/152% 10 100%

7 AD kickers platform removal sub-WP 1: Displace Electronics & Controls of AD Injection and Ejection Kickers to B393 Person in charge: Alain Antoine Budget of WU (kCHF): 550 Work Unit WU Start dateFinish dateAdvancement Budget Person reporting(dd/mm/yy) (% of total sub- WU) 2014201520162017 Perform electronics and controls displacement analysis Alain Antoine01/01/1430/06/1420 Produce engineering specificationAlain Antoine01/06/1430/06/1410 Purchase, produce & test required hardware Alain Antoine01/07/1431/12/1420100 Provide infrastructureAlain Antoine01/07/1430/03/1520150 Displace, reinstall & test electronics and controls Alain Antoine01/01/1531/05/1520 50 Commission systemAlain Antoine01/06/1530/06/1510 100 21/11/2014Cost&Schedule ELENA Beam Transfer7 Electronics&Controls displacement:

8 Injection kicker Electromechanical HW – 252 kCHF – 01/14 – 07/15 – Overspend on vacuum tank due to NEG coated additional parts instead of more simple tank coating + feedthrough (2x estimate, only one offer among 7 inquiries) – Vacuum tank delivery postponed by 6 months due to delay in drawings as the consequence of the delay in machine integration – Installation of vacuum tank in 06/15 will be tight – Spare magnets available (without tank) HV generators – 111 kCHF – 01/15 – 05/16 – Thyratrons purchase postponed for cost spreading – Common spare with AD ejection Electronics – 150 kCHF – 07/14 – 03/16 21/11/2014Cost&Schedule ELENA Beam Transfer8

9 Injection kicker sub-WP 1: ELENA injection kicker electromechanical hardware405.270475.60880.0000.000 Person in charge:Luc Sermeus Budget of WU (kCHF):252 Work Unit WU Start dateFinish dateAdvancementBudget Person reporting(dd/mm/yy) (% of total sub-WU)2014201520162017 Perform System DesignLuc Sermeus01/01/1431/03/140% Perform Detailed Engineering designLuc Sermeus01/04/1431/05/145%13 Write technical specificationLuc Sermeus31/05/1430/06/150% Contact EN-MME for vacuum tank and accessoriesLuc Sermeus01/06/1415/07/140% Manufacture vacuum tankLuc Sermeus15/07/1431/03/1569%8293 HV feedthroughs (1+S)Luc Sermeus01/09/1431/01/1512% 29 Perform vacuum tank testsLuc Sermeus01/04/1530/04/150% Connection boxes (1+S)Luc Sermeus01/01/1431/12/147%17 Perform assembly at CERNLuc Sermeus01/04/1531/05/150% Terminating resistorLuc Sermeus01/01/1531/05/153%215 Perform installation in situLuc Sermeus01/06/1509/06/150% 1 CommissioningLuc Sermeus01/07/1531/07/154% 10 100% 21/11/2014Cost&Schedule ELENA Beam Transfer9 sub-WP 2: Provide Electronics & Controls for ELENA Injection Kickers Person in charge:Alain Antoine Budget of WU (kCHF):150 Work Unit WU Start dateFinish dateAdvancementBudget Person reporting(dd/mm/yy) (% of total sub-WU)2014201520162017 Perform electronics and controls designAlain Antoine 01/07/1431/12/14 20 Produce engineering specificationAlain Antoine01/12/1431/12/1410 Purchase, produce & test hardwareAlain Antoine 01/01/1530/06/1530 2080 Provide infrastructureAlain Antoine 01/07/1530/09/1510 25 Install & test hardware and controlsAlain Antoine01/10/1531/12/1520 25 Commission systemAlain Antoine01/01/1630/03/1610 100 Injection kicker Electronics & Controls:

10 Injection Septum Magnet – 45 kCHF – 01/14 – 12/15 Electronics – 30 kCHF – 01/15 – 03/16 Power supply  EPC No issues expected 21/11/2014Cost&Schedule ELENA Beam Transfer10

11 Injection septum sub-WP 1: Provide Electronics & Controls for ELENA Septa Person in charge: Alain Antoine Budget of WU (kCHF): 30 Work Unit WU Start dateFinish dateAdvancement Budget Person reporting(dd/mm/yy) (% of total sub-WU) 2014201520162017 Perform electronics and controls design Alain Antoine01/01/1528/02/1520 Produce engineering specificationAlain Antoine01/03/1531/03/1510 Purchase, produce & test electronics and controls Alain Antoine01/04/1530/06/1530 10 Provide infrastructureAlain Antoine01/07/1530/09/1510 Install & test electronics and controls Alain Antoine01/10/1531/12/1520 10 Commission system Alain Antoine 01/01/1630/03/1610 100 21/11/2014Cost&Schedule ELENA Beam Transfer11 Provide ELENA injection septumELENAPjan.borburgh@cern.ch1-Jan-201431-Dec-2015reuse existing SM12 drawings9926415kCHF mechnical support9926425kCHF bus bar992645kCHF mechanical drawings0100%1-Jan-201420-Dec-2014 parts procurement0100%1-Jul-201530-Sep-2015 Installation01u1-Oct-201530-Dec-2015 Injection septum Electronics & Controls:

12 Overview 21/11/2014Cost&Schedule ELENA Beam Transfer12

13 Ion switch 1 unit + spare electrodes, insulators 150 kCHF 01/13 – 06/16 Assembly being finished in the Main Workshop Powering – Test supplies purchased – Final power supplies  EPC (might re-use test power supplies) Test stand with source if possible at final source location – 04/15 – Location of test stand to be defined – compatibility with other works and safety – Rely on external source delivery for test schedule – Rely on extended source instrumentation for beam tests – Final support should be ready – Test procedure to be prepared by beginning 2015 21/11/2014Cost&Schedule ELENA Beam Transfer13

14 Ion switch sub-WP 4:Ion switch Person in charge:Wolfgang Bartmann Budget of WU (kCHF):150 Work Unit WU Start dateFinish dateAdvancementBudget Person reporting(dd/mm/yy) (% of total sub- WU)2014201520162017 Perform System DesignWolfgang Bartmann01/01/1301/06/130% Perform Detailed Engineering designWolfgang Bartmann01/06/1301/05/1417%26 Write technical specificationWolfgang Bartmann01/12/1301/05/140% Manufacture electrodes, connectors, feedthroughsWolfgang Bartmann01/06/1401/12/1460%90 Perform assembly at CERN of electrodes and discsWolfgang Bartmann01/12/1419/12/143%5 Verify alignment precision of electrodes wrt discsWolfgang Bartmann08/01/1515/01/151%2 Slide electrode units into chambersWolfgang Bartmann15/01/1501/02/151% 2 Acceptance test (geometry, leak test, electrical test)Wolfgang Bartmann01/02/1501/03/150% Install at provisional test stand in AD hallWolfgang Bartmann01/04/1501/05/153% 5 Perform test with sourceWolfgang Bartmann01/05/1501/08/157% 10 CommissioningWolfgang Bartmann01/04/1601/06/167% 10 100% 21/11/2014Cost&Schedule ELENA Beam Transfer14

15 Fast Deflectors Deflector – 9 units + spare electrodes – 522 kCHF – 2 units for ring (Phase 1): 01/14 – 11/15 – 7 units for TLs (Phase 2): 01/15 – 11/16 – Long lead items ordered – No issues expected Powering – 9 units + 3 spares – 600 kCHF – Ring (2+1, Phase 1): 07/14 – 03/16 – TL (7+2, Phase 2): 07/14 – 06/17 – No issues expected 21/11/2014Cost&Schedule ELENA Beam Transfer15

16 Fast deflector 21/11/2014Cost&Schedule ELENA Beam Transfer16 Provide ELENA Fast Deflector ELENA ringELENAPjan.borburgh@cern.ch1-Jan-201430-Nov-2015 2 deflectors left, no spare tank9926450kCHF electrodes9926430kCHF feedthroughs9926416kCHF vacuum equipement9926420kCHF mechanical drawings100 %1-Jan-201430-Nov-2014 was included in job on 99260 parts procurement0100%1-Dec-201430-Apr-2015 vacuum chambers02U1-Jan-20151-May-2015 system assembled02U1-Jan-20141-Oct-2015TTE cost included system tested02U1-Sep-201530-Nov-2015 Provide ELENA Fast Deflectors TLELENAPjan.borburgh@cern.ch1-Jan-201530-Nov-2016 7 deflectors +1 spare left +1 spare right tank99264175kCHF electrodes99264105kCHF feedthroughs9926456kCHF vacuum equipement9926470kCHF parts procurement0100%1-Jan-201530-Dec-2015TTE cost included vacuum chambers07U1-Jan-20151-May-2015 system assembled07U1-Jan-201631-Jul-2016TTE cost included system tested07U1-Aug-201630-Nov-2016

17 Fast deflector powering 21/11/2014Cost&Schedule ELENA Beam Transfer17 sub-WP 1: Provide High Voltage Pulsed Generator and Electronics & Controls for ELENA Fast Switching Dipoles Person in charge: Tony Fowler Budget of WU (kCHF): 450 Work Unit WU Start dateFinish dateAdvancement Budget Person reporting(dd/mm/yy) (% of total sub-WU) 2014201520162017 Perform pulse generator design Tony Fowler01/07/1431/12/1410 30 Perform electronics and controls design Tony Fowler01/07/1431/12/1410 Produce engineering specification Tony Fowler01/12/1431/12/1410 Purchase, produce & test hardware Tony Fowler01/07/1530/06/1630 135 Provide infrastructure Tony Fowler01/07/1630/09/1610 45 Install & test hardware and controls Tony Fowler01/10/1631/12/1620 105 Commission system Tony Fowler01/04/1730/06/1710 100 sub-WP 3: Provide High Voltage Pulsed Generator and Electronics & Controls for ELENA Ejection Kickers Person in charge: Tony Fowler Budget of WU (kCHF): 150 Work Unit WU Start dateFinish dateAdvancement Budget Person reporting(dd/mm/yy) (% of total sub-WU) 2014201520162017 Perform pulse generator design Tony Fowler01/07/1431/12/1410 Perform electronics and controls design Tony Fowler01/07/1431/12/1410 Produce engineering specification Tony Fowler01/12/1431/12/1410 Purchase, produce & test hardware Tony Fowler01/01/1530/06/1530 45 Provide infrastructure Tony Fowler01/07/1530/09/1510 15 Install & test hardware and controls Tony Fowler01/10/1531/12/1520 35 Commission system Tony Fowler01/01/1630/03/1610

18 Quadrupole assembly Phase 1 – 15 units – 200 kCHF – 01/13 – 06/16 – Order placed, items should arrive end of this year, assembly and acceptance test tight but feasible until mid-15 Phase 2 – 49 units – 540 kCHF – 12/14 – 06/17 – No issues expected 21/11/2014Cost&Schedule ELENA Beam Transfer18

19 Quadrupole assembly sub-WP 1: Quadrupole assembly (Phase 1) Person in charge:Wolfgang Bartmann Budget of WU (kCHF):200 Work Unit WU Start dateFinish dateAdvancementBudget Person reporting(dd/mm/yy) (% of total sub-WU)2014201520162017 Perform System DesignWolfgang Bartmann01/01/1301/06/130% Perform Detailed Engineering designWolfgang Bartmann01/06/1301/08/1415%30 Write technical specificationWolfgang Bartmann01/06/1401/09/140% Perform Invitation to tenderWolfgang Bartmann01/09/1401/12/140% Manufacture electrodes, connectors, feedthroughsWolfgang Bartmann01/12/1401/03/1568%4294 Perform assembly at CERN of electrodes and discsWolfgang Bartmann01/03/1501/04/153% 6 Verify alignment precision of electrodes wrt discsWolfgang Bartmann01/04/1501/05/152% 3 Slide disc units into chambersWolfgang Bartmann01/05/1501/06/151% 2 Acceptance test (geometry, leak test, electrical test)Wolfgang Bartmann01/05/1501/06/152% 3 CommissioningWolfgang Bartmann01/03/1601/06/1610% 20 100% sub-WP 2: Quadrupole assembly (Phase 2) Person in charge:Wolfgang Bartmann Budget of WU (kCHF):540 Work Unit WU Start dateFinish dateAdvancementBudget Person reporting(dd/mm/yy) (% of total sub-WU)2014201520162017 Manufacture electrodes, connectors, feedthroughsWolfgang Bartmann01/12/1401/12/1576% 300110 Perform assembly at CERN of electrodes and discsWolfgang Bartmann01/03/1601/06/169% 406 Verify alignment precision of electrodes wrt discsWolfgang Bartmann01/06/1601/07/164% 202 Slide disc units into chambersWolfgang Bartmann01/07/1601/09/162% 102 Acceptance test (geometry, leak test, electrical test)Wolfgang Bartmann01/09/1601/10/160% CommissioningWolfgang Bartmann01/04/1701/06/179% 50 100% 21/11/2014Cost&Schedule ELENA Beam Transfer19

20 Electrostatic bends 10 units + spare electrodes 1222 kCHF 01/14 – 06/17 Engineering design to be finished mid next year Manufacture electrodes from end next year until mid-16 – Potential hardware contribution announced by Cockroft Institute – CERN technical documentation ready for tendering 06/15 21/11/2014Cost&Schedule ELENA Beam Transfer20

21 Electrostatic bends sub-WP 3:Electrostatic bends Person in charge:Wolfgang Bartmann Budget of WU (kCHF):1222 Work Unit WU Start dateFinish dateAdvancementBudget Person reporting(dd/mm/yy) (% of total sub- WU)2014201520162017 Perform System DesignWolfgang Bartmann01/01/1401/12/140% Perform Detailed Engineering designWolfgang Bartmann01/12/1401/06/152% 30 Write technical specificationWolfgang Bartmann01/04/1501/06/150% Perform Invitation to tenderWolfgang Bartmann01/06/1501/09/150% Manufacture electrodes, connectors, feedthroughs for 10 bendsWolfgang Bartmann01/11/1501/06/1676% 212720 Perform assembly at CERN of electrodes and framesWolfgang Bartmann01/06/1601/07/169% 110 Verify alignment precision of electrodes wrt framesWolfgang Bartmann01/07/1601/08/162% 30 Assemble electrode units into tankWolfgang Bartmann01/08/1601/09/161% 10 Acceptance test (geometry, leak test, electrical test)Wolfgang Bartmann01/09/1601/10/162% 30 CommissioningWolfgang Bartmann01/04/1701/06/177% 80 100% 21/11/2014Cost&Schedule ELENA Beam Transfer21

22 TL design Integration drawings for certain lines to be paid by workpackage Inj.Extr. Tls This did likely not appear in any of the initial cost estimates 21/11/2014Cost&Schedule ELENA Beam Transfer22 sub-WP 4:TL design Person in charge:Wolfgang Bartmann Budget of WU (kCHF):55 Work Unit WU Start dateFinish dateAdvancementBudget Person reporting(dd/mm/yy) (% of total sub- WU)2014201520162017 Perform TL DesignWolfgang Bartmann01/01/1301/12/140% Perform Detailed Integration designWolfgang Bartmann01/06/1301/05/16100%1520 100%

23 Potential issues/risks I AD kicker platform removal – Platform removal (“point of no return”): 12/14 – Transmission cable delivery (1km) not guaranteed for end 03/15  Decision if existing cables are removed for recuperation or not by 02/15 – Very tight schedule with AD operation prolongated up to mid December – Highly dependant of services : EN-HE for Transport, TE-VSC for cleaning EN-MME for central workshop – Risk for delay of AD startup in 2015 ELENA injection – Potential delay of injection kicker installation date June/15 – to be adapted in installation planning 21/11/2014Cost&Schedule ELENA Beam Transfer23

24 Potential issues/risks II Ion switch – Location of test stand to be defined – compatibility with other works and safety – Rely on external source delivery for test schedule – Rely on extended source instrumentation for beam tests Electrostatic bends – Technical documentation not finished  cost estimate less accurate than for other items – Cockroft Institute contribution to be clarified 21/11/2014Cost&Schedule ELENA Beam Transfer24