Presentation is loading. Please wait.

Presentation is loading. Please wait.

PRODUCTION COSTING W.D. Prasad Lecturer Dept. of Electrical Engineering University of Moratuwa.

Similar presentations


Presentation on theme: "PRODUCTION COSTING W.D. Prasad Lecturer Dept. of Electrical Engineering University of Moratuwa."— Presentation transcript:

1 PRODUCTION COSTING W.D. Prasad Lecturer Dept. of Electrical Engineering University of Moratuwa

2 Introduction Electricity generation system planning requires minimization of the total cost of supplying the demand during a specified period of time. Short term, Medium term or Long term. Medium term and Long term planning initial investment cost + production costs Short term planning production cost only

3 Load and Generator Models Production costing includes probabilistic treatment of the system load and the generation unit availability in almost all planning models. Chronological load curve Load duration curve Chronological load curve is modified with a plot of load versus the duration that the system load exceeds that load level. This curve can be converted to a probability curve, F(x) by dividing the horizontal axis (x- axis) by the total duration of the chronological load profile, T and rearranging the axes (Load Duration Curve, LDC).

4 Load and Generator Models Cont… Generators are normally represented by a two-state model where either a generating unit is available at its full capacity or not available. p i - Availability q i -FOR 0 C i ; C i = Capacity Probability associated with the state where the unit is not available is called Forced Outage Rate (FOR).

5 Production Cost Calculation Generators are first ranked according to their average incremental costs so that the units with the lower costs are placed at the top of the list (Merit Order). These units are now gradually loaded onto the LDC in merit order. After loading each generator the Effective Load Duration Curve (ELDC), F i can be obtained. The area under each of these ELDCs multiplied by the normalizing value, T, directly indicates the energy not served in the system. Unserved energy (UE i ) after loading the generator i is given by, Where T is the total duration

6 Production Cost Calculation Cont… Once the unserved energies are known the difference in unserved energies before and after loading a generator can be used to obtain the energy served by that generator. Energy produced by generator i, E i is given by, Corresponding production cost, Cost i is given by where IC i is the incremental cost of generator i Total production cost, TC is given by Where ng is the number of generator units

7 Multiple Availability States of Generators In most practical circumstances some of the generation units are likely to be deliberately operated at output levels below their full capacities during operation. Consider a generating unit model with two availability states. New ELDC will be In the case of a generator with multi-level availability states where n is the no. of availability levels

8 System Unserved Energy and Loss of Load Probability After loading all the generating units onto the load curve there will be a final ELDC left behind. Loss of Load Probability (LOLP) is the probability that the system generation is not able to supply the system load either fully or partially. This can be directly obtained from the final ELDC.

9 The total energy left to be served after loading all the generating units is called the Expected System Unserved Energy. Average cost of losses due to the power supply failures is called the Value of Lost Load (VLL) which is given in Rs/ kWh not supplied. System planners need to add new generating units into the system until the following condition is satisfied.

10 Example 1)[a] Determine LOLP, EUE and total production cost if the system load given in Table 1 is supplied with generators in Table 2. Time (hrs) 00-0303-0606-0909-1212-1515-1818-2121-24 Load (MW) 300 400600 400300 Table 1: Load Variation GeneratorIncremental Cost (Rs/MWh) Capacity (MW)Forced Outage Rate Generator 18003000.05 Generator 210002500.05 Generator 312002000.1 Table 2: Generator Data

11 Answer Cost (Rs/MWh)80010001200 FOR0.05 0.1 Capacity300250200 Load (x)Duration (hrs)F 0 (x)F 1 (x)F 2 (x)F 3 (x) 02410.643750.4181250.076125 502410.643750.0618750.0405 1002410.406250.050.0224375 1502410.406250.0381250.00521875 2002410.406250.0381250.00465625 2502410.406250.0381250.00465625 300150.6250.031250.0193750.00278125 350150.6250.031250.0015630.001 40090.3750.018750.0009380.00009375 45090.3750.018750.0009380.00009375 50090.3750.018750.0009380.00009375 55090.3750.018750.0009380.00009375 60000000 Unserved Energy (MWh)105003660802.875189.3 Energy Served (MWh)68402857.125613.575 Production Cost (Rs)54720002857.125736290 LOLP7.6 % EUE (MWh)189.3 Total Production Cost (Rs)9065415

12 b] Comment on possible changes to the answers in (a) if generator 2 and 3 are replaced with generator 4 given in Table 3 having an incremental cost of 1100 Rs/MWh Table 3: Generator 4 Data Capacity (MW) 0200250450 Probability0.0050.0450.0950.855

13 Answer When generators 2 and 3 are combined the resultant generator will have an availability distribution with four levels of operation as given below. This distribution is exactly the same as the generator 4 distribution given. Thus even though the generators 2 and 3 are replaced with the generator 4, the final probability distribution will not change. This means that the LOLP and the expected system unserved energy also will not be modified. However, the production cot will change due to the modified incremental cost. Total energy served by generator 2 & 3= 3470.7 MWh Total production cost of generator 2 & 3= Rs 3593415 Energy served by generator 4= 3470.7 MWh Production cost of generator 4= Rs 3817770 Generation Level (MW) 0200250450 Probability


Download ppt "PRODUCTION COSTING W.D. Prasad Lecturer Dept. of Electrical Engineering University of Moratuwa."

Similar presentations


Ads by Google