Highest Priority Projects from “Immediate Action” Category Immediate Action All Others.

Similar presentations


Presentation on theme: "Highest Priority Projects from “Immediate Action” Category Immediate Action All Others."— Presentation transcript:

1

2 Highest Priority Projects from “Immediate Action” Category Immediate Action All Others

3 Highest Priority Project Status Project ID – NameInvestigation Status B-River Road Force MainUnderway (CDM) C-PS12 Force MainUnderway (CDM) D-PS10 Force MainUnderway (CDM) G-Burnt Mill Creek OutfallUnderway (CDM) K-Downtown Sewershed 11Underway (CDM) M-Outfall South of Greenfield Lake to PS14Underway (CDM) I-Front Street InterceptorUnderway (CDM) F-Pump Station 11Complete J-Downtown Sewers Contributing to PS9Complete A-Northeast Interceptor (NEI)Underway (KH) E-Pump Station 34Underway (KH) H-McCumber’s Ditch OutfallComplete, Rehabilitated L-Mineral Springs InterceptorComplete, Rehabilitated

4 Project B: River Road Force Main u 18,500 feet u 20- and 24- inch Pipe u PCCP and DIP

5 Project C: Pump Station 12 Force Main u 5,300 feet u 20-inch DIP 5,300 Feet

6 Project D: Pump Station 10 Force Main u 5,300 feet u 30-inch DIP u Elevated Over Smith Creek

7 Ultrasonic Investigations of Ductile Iron Pipe Were Performed to Identify Corrosion Problems

8 Pipe Coupons Provide Ultrasonic Calibration and Corrosion Verification

9 Gravity Sewer Investigation u Manhole and Zoom Camera Inspection

10 Project G: Burnt Mill Creek Outfall u 3,100 Feet u 48-inch RCP/DIP u 18 Manholes

11 Project K: Downtown Sewer Contributing to PS11 u 1,300 Feet 6- inch u 25,600 Feet 8- inch u 500 Feet 10- inch u 1,400 Feet 12- inch u 131 Manholes

12 Project M: Outfall to PS14 South of Greenfield Lake u 7,500 Feet u 12-inch VCP u 30 Manholes

13 Project I: Front Street Interceptor u 3,400 Feet u 15 & 18-inch VCP/RCP u 15 Manholes

14 Current Phase 2 Status and Schedule: u Completed Field Investigation of High Priority Projects u Analyzing Results and Preparing Conclusions u Present Results and Conclusions to Council next week u Draft report in November with recommendations and costs u Update to Council with recommendations and costs in December


Download ppt "Highest Priority Projects from “Immediate Action” Category Immediate Action All Others."