1857 Standards Progress IEEE 1857 Working Group May 17, 2015.

Similar presentations


Presentation on theme: "1857 Standards Progress IEEE 1857 Working Group May 17, 2015."— Presentation transcript:

1 1857 Standards Progress IEEE 1857 Working Group May 17, 2015

2 Pro/Std No.Short NamePAR approvedCurrent StatusEdc 1857-2013Video coding29-Mar-2012 Approved and published standards 1857a-2014Amend. 1 of 1857-201330-Aug-2013 1857.2-2013Audio coding02-Nov-2012 1857.3-2013System02-Nov-2012 P1857.42 nd Generation of Video11-Dec-2013 Preparation for WG vote P1857.5Mobile Speech and Audio11-Dec-2013 Sponsor ballot invitation P1857.6 Digital Media Content Description 11-Dec-201325% completedDec-2016 P1857.7Adaptive Streaming10-Dec-201450% completedDec-2015 Summary

3 Fruit

4 1857-2013 Standard for Advanced Audio and Video Coding-video Std. was approved on March 06, 2013, published on June 04, 2013 1857a-2014 Amendment 1 of IEEE Std. 1857-2013 Std. was approved on March 27, 2014, published on April 04, 2014 1857.2-2013 Standard for Advanced Audio Coding Std. was approved on Aug. 23, 2013, published on Nov.12, 2013 1857.3-2013 Standard for System of Advanced Audio and Video Coding Std. was approved on March 06, 2013, published on June 04, 2013 Standards

5 Active Projects (1) P1857.5 Standard for Advanced Mobile speech and Audio PAR was approved on Dec 11, 2013 The project is currently at the stage of sponsor ballot invitation and the enrollment will close at 11:59 p.m. Eastern Time 27-May-2015. P1857.4 Standard for 2nd Generation IEEE 1857 Video PAR was approved on Dec 11, 2013. The draft has been completed and will be voted in WG in early June next month.

6 Active Projects (2) P1857.6 Standard for Digital Media Content Description PAR was approved on Dec 11, 2013 The visual descriptors was 25% completed. There is no substantial progress in the last four months. One work meeting was convened on March 19, 2015 and three technical proposals were reviewed and adopted. The standard draft is expected to be finished by the end of 2016.

7 Active Projects (3) P1857.7 Standard for Adaptive Streaming PAR was approved on Dec 10, 2014 The draft has been 50% completed. The draft is expected to be fully completed in December 2015 The group is now working to 1) determine the protocols that should be supported besides HTTP; 2) determine the relationship between the HTTP part and other possible protocol based parts. The progress of the last four months: The accuracy, integrity and readability of the HTTP part has been carefully checked.

8 Thank you! May 17, 2015 http://www.ieee1857.org http://standards.ieee.org/develop/wg/AVS_1857_WG.html