Operations meeting on FY07 Shutdown Date: June 27, 2007. W.B. Christie Outline Brief Overview of Shutdown Plan Details/discussion of next few weeks Comments.

Similar presentations


Presentation on theme: "Operations meeting on FY07 Shutdown Date: June 27, 2007. W.B. Christie Outline Brief Overview of Shutdown Plan Details/discussion of next few weeks Comments."— Presentation transcript:

1 Operations meeting on FY07 Shutdown Date: June 27, 2007. W.B. Christie Outline Brief Overview of Shutdown Plan Details/discussion of next few weeks Comments on Working at the STAR site

2 June 27-July2: Remove Shield Wall (3.5 days, Riggers) June 27 – July 2: Remove Vacuum pipe spool pieces. July 3: Pull East Poletip July 5: Pull West Poletip. Install scaffolding E&W. (Charlie & Steve) June 27 – July 13: Remove SVT RDOs, extender cables, and cabling back to the Racks. Remove EEMC Trigger Cables. June 27 – July 18: Install Rollers and disconnect utilities, and roll STAR to AB and connect utilities. July 20 – Aug. 24: EEMC electronics maintenance. July 19 – 27: Install SVT platform, FTPC West platform, and disconnect end of cone cables, remove FTPCs, and extract cone to platform. July 30 – Aug. 14 : Remove SSD, SVT, all utilities on cone, and reassemble cone. Aug. 1 – 15: Install new BEMC PMT comm./controls system. Aug. 16-21: Reinstall cone, reinstall FTPCs, & remove rails. Remove installation platform. Aug. 22 – 27: Disconnect utilities. Aug. 28 - 29: Roll STAR back into IR. Aug. 30 – Sept. 10: Install Utilities. Draft STAR Shutdown Schedule/Plan Summer Sunday July 2007 August 2007

3 Sept. 6 – 18: Beam Pipe Bakeout Sept. 11 th : STAR in IR with utilities connected. Sept. 11 – Oct. 12: TPC Electronics maintenance. October 1 st : TOF Trays arrive at BNL for installation. Oct. 15 – 18: SGIS Certification. Oct. 17 th : West Poletip installed. Oct. 24: East Poletip installed. Oct. 25 – 30: Magnet testing. Nov. 1 st : Collider Cooldown Begins. Nov. 1 – 2: Install BBCs. Nov. 7 th : Lose access to IR for Collider Commissioning. Still Open: * When/where best to install TOF trays? Best locations 2, 4, 7, & 10:00. * Details/plan for the TOF water system? Collider Cooldown Begins September 2007 October 2007

4 June July Dates/Tasks: 27 th – Install Hydraulic sys. Pressure gauges 28 th – Remove BBC’s, remove VPDs, start on EEMC Trigger cable removal. 29 th – Start Vacuum pipe spool pieces removal (East first), continue EEMC effort. Dates/Tasks: 2 nd – Start removal of Shield wall. Continues till ~ Thursday noon. - Start removal of TPC pipes/utilities - removal of Magnet water lines, and blow out coils 3 rd – Continue TPC utilities removal (finish?) - Start West SVT RDO removal (?) 5/6 th – Remove East Poletip 9 th – 17 th – Pull West Poletip, Remove SVT RDOs, drop all water/gas/power connections, install Hillman Rollers, Remove stairs and Bridge for move. 18 th – Planned date for Rolling STAR to AB.

5 General Comments on Work in the STAR Facility Work Planning: - N.B. All work undergoes Work Planning. Most of this is what’s known as Worker Planned work. Before you start on a task think about what you’re going to do, how you’re going to do it, what the hazards are, and how you’ll minimize these possible Hazards. - As a General rule, Bob or Bill should always know who will be working in the Facility, and on what, every week. Please make every effort to keep us informed. Safety: - All work should be performed in compliance with Safety rules. If there is a conflict between schedule and Safety, Safety must take precedence in all cases. - If anyone is ever in doubt about how to perform a task, please contact Bob, Bill, or both. - In the course of accomplishing your tasks throughout the Shutdown, if anything becomes apparent on how we could work safer, please bring them to Bill or Bob’s attention. - If you see anyone doing something that appears unsafe, or somehow incorrect, please bring it to Bob or Bill’s attention. Housekeeping: - In performing work in the STAR Facility please clean up after yourself at the end of each day. Examples are picking up cable tie remnants, paper from Label makers, misc. “litter” that results from your work.


Download ppt "Operations meeting on FY07 Shutdown Date: June 27, 2007. W.B. Christie Outline Brief Overview of Shutdown Plan Details/discussion of next few weeks Comments."