1 Employee Productivity. 2 ProductivityProductivity l Productivity means the amount of products or services produced with the resources used l Productivity.

Similar presentations


Presentation on theme: "1 Employee Productivity. 2 ProductivityProductivity l Productivity means the amount of products or services produced with the resources used l Productivity."— Presentation transcript:

1 1 Employee Productivity

2 2 ProductivityProductivity l Productivity means the amount of products or services produced with the resources used l Productivity = Quantity of products or services produced Amount of resources used Amount of resources used l Productivity varies with the amount of production relative to the amount of resources used.

3 3 Ways to Increase Productivity l Increase output using the same or a lesser amount of resource. l Reduce amount of resource used while keeping output constant or increasing it. l Use more resource as long as output increases at a greater rate. l Decrease output as long as resource use decreases at a greater rate.

4 4 Impact of Price/Cost Change on Productivity l When the cost of a resource increases and profit is to remain the same, some combination of the following must occur: l output is increased l resource usage is decreased l price of output is increased

5 5 Why do We Care About Productivity? l Without productivity improvement, businesses do not survive in a global economy. l Higher productivity means higher standard of living. l The US has traditionally been the leader in productivity gains but other countries are closing the gap.

6 6 Single Factor Approach to Measuring Productivity l Capital - Number of products produced divided by asset value divided by asset value l Materials - Number of products produced divided by dollars spent on materials divided by dollars spent on materials l Direct Labor - Number of products produced divided by direct labor-hours l Overhead - Number of products produced divided by dollars spent on overhead divided by dollars spent on overhead

7 7 Single Factor Approach to Measuring Productivity l Note that the productivity of a particular resource can be increased simply by replacing some of this resource with a different type of resource. l For example: If automation is substituted for direct labor and output volume is unaffected, direct-labor productivity increases (and capital productivity decreases). l Our view of productivity must be toward improving the productivity of all the factors of production.

8 8 Labor Productivity l For some firms, production labor (touch labor) represents a very small part of the firm’s total costs l For other firms, particularly service firms, direct labor cost remains a significant cost and the need to improve labor productivity is still a serious concern

9 9 Variables Affecting Labor Productivity l Physical work environment l Technology, equipment, materials, lighting, layout l Product quality l Defects, scrap, rework l Employee job performance l Employee ability, motivation

10 10 Employee Job Performance l Motivation is perhaps the most complex variable in the productivity equation. l Only unsatisfied needs are motivators. l Maslow identified five basic needs: physiological, safety, social, esteem, and self-fulfillment. l The higher level needs (social, esteem, and self- fulfillment) might hold the most promise for motivating. l If productivity is seen as a way to fulfill needs, higher productivity is likely to result.

11 11 MotivationMotivation l Formal organization l Informal groups l Job design l Leadership l Union l Psychological needs l Economic conditions l Personal situations

12 12 Specialization of Labor l Advantages l High production rates l Low wage rates l Low skill requirements l Disadvantages l High turnover, absenteeism, tardiness, grievances, sickness, and sabotage l Low production quality

13 13 Modifying Jobs to Provide Broader Range of Needs Satisfaction l Cross-training -- workers perform multiple jobs l Job enlargement -- adding similar tasks to worker’s job - horizontal job expansion l Job enrichment -- adding more management functions to job - vertical job expansion l Team production -- organizing workers into teams; assigning management responsibility to teams

14 14 Job Design l Can we simultaneously give workers the satisfaction they want from their work and still give the organization the productivity and efficiency to survive economically?

15 15 Guidelines for Designing Jobs and Work Environments Workers’ Job Tasks l Avoid machine pacing of workers l Design jobs so that workers inspect their own output l Open work areas for communication & visual contact l Combine job planning into workers’ jobs l Automate boring, uncomfortable, or unsafe jobs

16 16 Guidelines for Designing Jobs and Work Environments Immediate Job Setting l Rotate jobs that are repetitive, monotonous, boring l Assign new workers to undesirable jobs, then transfer them to more preferred jobs l Recruit disadvantaged persons for high-turnover jobs l Give rest periods to workers with repetitive jobs l Set higher pay rates for undesirable jobs

17 17 Guidelines for Designing Jobs and Work Environments Larger Work Environment l Select/train supervisors who openly communicate l Develop supervisors who are comfortable with a participative team environment l Remove physical barriers between management and other employees l Create climate that recognizes workers & work teams l Develop formal/informal channels of communication in all directions

18 18 Empowering Workers l It is the employees who have control of, and know the most about, the details of production. l To get employees to accept this responsibility, managers must first give employees the authority to act. l The process of conveying authority from managers to workers is called worker empowerment. l Workers accepting responsibility for production can lead to what is called internal ownership.

19 19 Steps of Work Methods Analysis 1. Make an initial investigation of the operation 1. Make an initial investigation of the operation 2. Decide what level of analysis is appropriate 2. Decide what level of analysis is appropriate 3. Get suggestions from anyone familiar with operation 3. Get suggestions from anyone familiar with operation 4. Thoroughly describe and evaluate present method 4. Thoroughly describe and evaluate present method 5. Devise a new proposed method 5. Devise a new proposed method 6. Compare new and present methods 6. Compare new and present methods 7. Modify the proposed method 7. Modify the proposed method 8. Perform the proposed method on a trial basis 8. Perform the proposed method on a trial basis 9. Install the proposed method and train workers 9. Install the proposed method and train workers 10. Check on new method periodically

20 20 Work Measurement l Work measurement refers to the process of estimating the amount of worker time required to produce one unit of output. l A goal of work measurement is to develop labor standards that can be used for planning and controlling operations.

21 21 Labor Standards l A labor standard is the number of worker-minutes required to complete an element, operation, or product under ordinary operating conditions. l Ordinary operating conditions refers to a hypothetical average situation ….. average or typical worker, material, machinery, environment, etc.

22 22 Labor Standards l Labor standards are used in: l Cost estimation l Pricing of products and services l Incentive pay systems l Capacity planning l Production scheduling

23 23 Labor Standards l A labor standard can be determined using one or more of the following approaches: l Time study l Work sampling l Predetermined time standards ----------- subjective ------------ l Historical standards l Supervisor estimates

24 24 Time Study Suitable Jobs l Job performed by a single worker in a fixed location l Job involves repetitive short cycles l Job expected to continue unchanged for a long period l Job produces large quantities of output l Resulting time standard must be very accurate

25 25 Time Study l Analysts use stopwatches to time the operation being performed by workers l These observed times are then converted into labor standards l The labor standards are expressed in minutes per unit of output for the operation

26 26 Determining Labor Standards from Time Studies ObservedTimeObservedTimeNormalTimeNormalTimeStandardTimeStandardTime Performance PerformanceRating RatingAllowanceFractionAllowanceFraction

27 27 Determining Labor Standards from Time Studies 1. Make sure correct methods are being used to perform the operation being studied. 2. Break the operation down into basic tasks (elements). 3. Determine how many cycles to time. A cycle is one complete set of the elemental tasks. 4. Observe and record the elapsed time for each element for the number of required cycles.... more... more

28 28 Determining Labor Standards from Time Studies 5. For each element, estimate the observed worker’s performance rating. A rating of 1.00 indicates the worker is working at normal speed. 6. Compute the allowance fraction for the operation. The allowance fraction is the fraction of time that workers cannot work through no fault of their own.... more... more

29 29 Determining Labor Standards from Time Studies 7. Compute the mean observed time for each element: (Sum of observed element times) (Number of cycles timed) (Number of cycles timed) 8. Compute the element normal time for each element: = (Mean observed time) x (Performance rating) = (Mean observed time) x (Performance rating)... more =

30 30 Determining Labor Standards from Time Studies 9. Compute the total normal time for the entire operation: = (Sum of element normal times for all elements) = (Sum of element normal times for all elements) 10. Compute the labor standard for the operation: = (Total normal time) / (1 - Allowance fraction) = (Total normal time) / (1 - Allowance fraction)

31 31 Work Sampling l The work of one or more employees is randomly sampled at periodic intervals l Noted is the proportion of the total operation that is accounted for in one particular activity l The results of these studies are used to: l Set allowances used in labor standards l Set labor standards

32 32 Work Sampling Suitable Jobs l Job performed by a single worker in a fixed location l Job involves repetitive short cycles l Job expected to be changed periodically as customer orders change l Job produces relatively small quantities of output l Resulting time standard used for accounting cost standard, pricing analysis, and production planning

33 33 Predetermined Time Standards l Commonly used for new operations or new products l When labor standard must be determined in advance of performing an operation l Utilize data that have been historically developed for basic body movements, elements of operations, and entire operations l Many predetermined time standard systems are used: l Work factor l Methods-time measurement (MTM) l Basic motion time (BMT) study l … and others

34 34 Predetermined Time Standards Suitable Jobs l Job performed by many workers over a compact area l Tasks may involve little repetition, but if repetitious – the cycles are very long l Workers must be observed by a single analyst l A moderate degree of accuracy in the labor standard is desirable, but a time study is too costly l Only large elements of work need to be observed l Little detail is needed in setting the time standard

35 35 Subjective Methods Suitable Jobs Any job or group of jobs in which: l Very accurate labor standards are not required, or l The cost of time study, predetermined time standards, and work sampling is prohibitive

36 36 Learning Curves At the start of production runs: l Workers are unfamiliar with their tasks l Time it takes to produce the first few units is high As the workers learn their tasks: l Their output per day increases up to a point l Then their output levels off to a rather constant rate

37 37 Learning Curves l Most aircraft manufacturing tasks experience an 80% learning rate l Labor-hours required to assemble an aircraft is reduced by a factor of 0.8 as the production quantity doubles l If first aircraft assembled requires 100 labor-hours l Second aircraft would require 80 labor-hours l Fourth aircraft would require 64 labor-hours l Eighth aircraft would require 51.2 labor-hours l … and so on

38 38 Learning Curves 10 20 30 40 50 60 70 80 90 100 110 120 130 20 80 40 100 60 Unit Number (n) 120 Labor-Hours for nth Unit Aircraft Assembly 80% Learning Curve

39 39 Learning Curves By analyzing workers’ learning situations, we are able to estimate: l The average number of labor-hours required per unit for N units in a production run l The total number of labor-hours required to produce N units in a production run l The exact number of labor-hours required to produce the nth unit of a production run

40 40 Learning Curves Three approaches to learning-curve problems are: l Arithmetic analysis l Logarithmic analysis l Learning curve tables

41 41 Learning Curves Arithmetic Analysis l The simplest approach to learning-curve problems l If we wish to find the labor-hours required to produce n units, and n just happens to be a number that is one of the doubled values, then this approach works

42 42 Learning Curves Learning-Curve Tables A table of learning curve coefficients (Table 18.12) allows us to compute: l The labor-hours for the nth unit in a production run l The total labor-hours for the entire production run, where the nth unit is the last unit in the run

43 43 Learning Curves l Selecting a learning rate l Industry journals l Historical experience l Uses and limitations l Products and services tend to be custom designed l Batches tend to be small l Product/services tend to be complex.... learning occurs quickly

44 44 Employee Health & Safety l Several regulations and government agencies monitor and control; l OSHA - safety and health in the workplace. Federal... pro-active l Worker’s Compensation - safety and health in the workplace. State.... re-active l EPA - Environmental protection outside of the workplace. Federal... pro-active l Safety and Health departments in plant

45 45 Wrap-Up: World-Class Practice l World class companies recognize employees are of strategic and tactical importance l Workers must have problem-solving abilities and be trained, cross-trained, educated and empowered so that they can work in teams and respond to customer needs l Organizational structure must be developed to encourage full use of employees l Information is the main media of management


Download ppt "1 Employee Productivity. 2 ProductivityProductivity l Productivity means the amount of products or services produced with the resources used l Productivity."