April 18, 2006FermiGrid Project1 FermiGrid Project Status April 18, 2006 Keith Chadwick.

Similar presentations


Presentation on theme: "April 18, 2006FermiGrid Project1 FermiGrid Project Status April 18, 2006 Keith Chadwick."— Presentation transcript:

1 April 18, 2006FermiGrid Project1 FermiGrid Project Status April 18, 2006 Keith Chadwick

2 April 18, 2006FermiGrid Project2 FermiGrid – Four Components FermiGrid Common Grid Services: Supporting common Grid services to aid in the development and deployment of Grid computing infrastructure by the supported experiments at FNAL FermiGrid Stakeholder Bilateral Interoperability: Facilitating the shared use of central and experiment controlled computing facilities by supported experiments at FNAL –CDF, D0, CMS, GP Farms. FermiGrid Development of OSG Interfaces for Fermilab: Enabling the opportunistic use of FNAL computing resources through Open Science Grid (OSG) interfaces. FermiGrid Exposure of the Permanent Storage System: Enable the opportunistic use of FNAL storage resources (STKEN) through Open Science Grid (OSG) interfaces

3 April 18, 2006FermiGrid Project3 FermiGrid1 - Globus Jobmanager Calls

4 April 18, 2006FermiGrid Project4 FermiGrid2 - voms-proxy-init’s by VO

5 April 18, 2006FermiGrid Project5 FermiGrid2 - voms_proxy_inits within fermilab VO

6 April 18, 2006FermiGrid Project6 FermiGrid3 - GUMS Metrics

7 April 18, 2006FermiGrid Project7 Fngp-osg - Globus jobmanager calls

8 April 18, 2006FermiGrid Project8 Stakeholder Discussions FermiGrid stakeholder meetings are regularly taking place on every other week in FCC1 on Mondays at 3:00pm (following the CD computer room planning meeting). Work is progressing on stakeholder bilateral interoperability:

9 April 18, 2006FermiGrid Project9 CDF Glide-CAF - fcdfosg1

10 April 18, 2006FermiGrid Project10 CDF Glide-CAF - fcdfosg2

11 April 18, 2006FermiGrid Project11 D0 OSG CAB Currently being commissioned.

12 April 18, 2006FermiGrid Project12 Permanent Storage System The FermiGrid OSG storage element FNAL_FERMIGRID_SE has been commissioned as part of the public dcache. The IA group is in the process of adding the necessary dcache user accounts. Requisition CD99397, totaling ~$64K, for 24 Tbytes of HDS SATA disk for attachment to the CD BlueArc NFS server appliance was submitted for approvals on Wednesday April 12, 2006.

13 April 18, 2006FermiGrid Project13 Development Systems FermiGrid0 Tanya Levshina is currently using fermigrid0 for her VOMRS/VOMS testing and development. This system is also available for use by other FermiGrid and Fermilab grid developers. Fgtest1-Fgtest5 We have five systems from the former QCD cluster. There are installed in WH8NE. Various tests are being done: –New versions of OSG (ITB 0.3.6 & 0.3.7) –High availability / Service redundancy –New job forwarding mechanisms –SAZ testing –glexec testing & development

14 April 18, 2006FermiGrid Project14 SAZ FermiGrid4: Recoded SAZ implementation is almost ready to go. Deployment Plan: Have a formal code review. Install SAZ server on FermiGrid4 Install SAZ client on fgtest1-5 and test for at least a week.

15 April 18, 2006FermiGrid Project15 glexec Needed by CDF Glide- CAF to meet Fermilab accounting, auditing, and security requirements. Existing glexec code uses LCMAPS+LCAS infrastructure from LCG and needs to be modified to interoperate with OSG GUMS+SAZ infrastructure. Dan Yocum is working on the WBS for the glexec recoding project.

16 April 18, 2006FermiGrid Project16 What is Next for FY2006?

17 April 18, 2006FermiGrid Project17 FermiGrid – Milestones & Time Line Apr 2006:CDF Glide-CAF Integration. May 2006:SAZ Testing & Deployment. glexec software design. Participation in OSG 0.3.6, 0.3.7 ITB, OSG 0.4.1 release. Revised FermiGrid border gateway job forwarding mechanism using OSG cemon and resource selection. FermiGrid OSG SE & public dcache deployment. June-July 2006Participation in OSG 0.5.0 ITB, OSG 0.6.0 release. glexec coding, test and deployment. BlueArc storage integration. Ongoing:Service redundancy / high availability configuration. Work with other Fermilab resources to integrate them into FermiGrid. Work with OSG to validate FermiGrid interoperability.

18 April 18, 2006FermiGrid Project18 FermiGrid – Fin Any questions?

19 April 18, 2006FermiGrid Project19 Globus Metrics - Flowchart