Pre-Grid Commissioning for Renewables Alf Scambler Renewables Sector Development Manager.

Similar presentations


Presentation on theme: "Pre-Grid Commissioning for Renewables Alf Scambler Renewables Sector Development Manager."— Presentation transcript:

1 Pre-Grid Commissioning for Renewables Alf Scambler Renewables Sector Development Manager

2 Main Grid Connection Delays Or Grid outages Solving project bottlenecks when grid delays occur. Simulation of Grid supply for commissioning of equipment. Can complete 99% of the commissioning. Can allow stage payments to be made. Keeps commissioning teams on site. Revenue generation for the developer as soon as grid is connected. O&M phase –Planned or unplanned grid outages, equipment can be kept healthy from the site HV network enabling maintenance, preservation of warranty and early resumption of power export to grid. 2

3 Power supplies - Low Voltage connection @ turbine 400 - 690V

4 Turbine “Cold Commissioning” Option – 110V, 240V,415V, and 690V

5 High Voltage connection resistive / reactive Load Bank – enables full load test of turbines 5 GEN 2 GEN 1 5 MVA Resistive Reactive Load bank CB 1 CB 2 Generator Controller Step up / down transformer Low voltage High voltage

6 33kV Full Load test single turbine package

7 Multiple turbine commissioning system | 7| 7

8 Solar Farm Commissioning Diesel Generator ~ Grid 33kV 50Hz 33kV 50Hz 415V 50Hz DC / AC LoadbankSigma controller

9 33kV package for turbine ancillary power support during unplanned mains outage 9

10 Bio Gas applications 10

11 Grid Simulation for Wind Solar / Wave / Tidal / Biomass / Gas

12 Belfast Portlaoise Port Talbot Nuneaton Bristol Plymouth M54 (WPD) Inverness Aberdeen Dumbarton Washington Manchester Doncaster Market Deeping (WPD) Great Yarmouth Bedford London Fareham National Rental Centre − 24/7 365 Operation − Service offering − Operational support − Sales / Technical support − Logistics support − Fuel management service − Invoicing services UK Locations Contact Tel. 08458 24/7/365 sales@aggreko.co.uk www.aggreko.co.uk


Download ppt "Pre-Grid Commissioning for Renewables Alf Scambler Renewables Sector Development Manager."