1 Project Management Terry A. Ring Chemical Engineering University of Utah

2 Waterfall Style of Project Management

3 Waterfall Style of Project Management with Recycle Loop

4 Agile Project Management Agile methodologies are proven to be 3x more successful than traditional waterfall methodologies and 2x faster

5 Estimating – Hours for Deliverables Scope of Work/Schedule Development 10 hrs for PFDs 10 hrs for Process Simulations & Equipment Data Sheets 5 hrs for P&IDs Development of Process Design Basis 20 hrs for PFDs Includes Plant Wide Control System Major Components of Safety System 10 hrs for Process Simulations 10 hrs for P&IDs PFDs 20 hrs for PFD Development 4 hrs/PFD for PFD Review 4 hrs/PFD for Materials of Construction Breaks

6

7

8 Estimating – Hours for Deliverables Scope of Work/Schedule Development 10 hrs for PFDs 10 hrs for Process Simulations & Equipment Data Sheets 5 hrs for P&IDs Development of Process Design Basis 20 hrs for PFDs Includes Plant Wide Control System Major Components of Safety System 10 hrs for Process Simulations 10 hrs for P&IDs PFDs 20 hrs for PFD Development 4 hrs/PFD for PFD Review 4 hrs/PFD for Materials of Construction Breaks

9 Estimation Process Simulations 2x PFD hours Includes H&MB Tables for PFDs Utilities Summary Feed and Effluent Summaries Could Increase for: Startup, Shutdown, Overdesign, Underdesign, Summer, Winter Operations, Impurity Dispositions P&IDs 80 hrs per Inside BL P&ID 40 hrs per Outside BL P&ID 20 hrs per Outside BL P&ID 8 hrs per Demolition P&ID In-house reviews 6 P&IDs per day for Design Team Reviews at 50% and 100% complete

10

11 Estimation Process Simulations 2x PFD hours Includes H&MB Tables for PFDs Utilities Summary Feed and Effluent Summaries Could Increase for: Startup, Shutdown, Overdesign, Underdesign, Summer, Winter Operations, Impurity Dispositions P&IDs 80 hrs per Inside BL P&ID 40 hrs per Outside BL P&ID 20 hrs per Outside BL P&ID 8 hrs per Demolition P&ID In-house reviews 6 P&IDs per day for Design Team Reviews at 50% and 100% complete 10%

12 Estimating Equipment List & Data Sheets 4 hrs. for Equipment List Formating Pumps & Compressors 6 hrs each on PFD 12 hrs each on P&ID Vessels/Tanks/Towers 4 hrs each on PFD 12 hrs each on P&ID Reactors 8 hrs each on PFD 24 hrs each on P&ID Heat Exchangers/Fin-Fans 4 hrs each on PFD 8 hrs each on P&ID Fired Heaters 16 hrs each on PFD 24 hrs each on P&ID Engineering Support for Vendor Requests and Non ChEs 30% of Hrs for Equipment List & Data Sheets Process Data for Piping 5% of Total P&ID hours 6 Hours for AIChE Project using Aspen/ProMax Equipment Data Sheets

13 Estimating Process Data for Process Instrumentation 2 hrs for each instrument 2 hrs for each Process Control Loop Process Safety Valve Design Assume 1 PSV per vessel 4 hrs per PSV Support for Cost Estimation Done by the Cost Estimation Team 5% of Hrs for Equipment List Items for PFD Items 5% of Hrs for Equipment List Items for P&ID Items HAZOP Analysis Review of 4 P&IDs per day 2 process engineers, 8 hrs/day AIChE Cost Estimation – 6 hrs

14 Estimating Supervision Supervision and Coordination 10% of a Process Engineering hrs for PFD development 5% of a Process Engineering hrs for P&ID development 5% of Process Engineering hrs for Equipment List and Data Sheets Piping Data Instrumentation PSV Designs Documentation/Data Books/Reports 5% of PFD hours 2% of P&ID hours Contingency + 10% of Total PFD hours + 10% of Total P&ID hours AIChE Project add 10% of total project time for Communication