1 Wind Power in Korea Seokwoo Kim, Ph. D (wemins@kier.re.kr) Korea Institute of Energy Research Daejeon, Korea

2 Founded in 1977 303 Research Scientists & Engineers Budget : 0.12 billion Euros in 2010 4 Divisions & 14 Centers

3 Wind Energy Research Center Research Areas - Wind Resource Assessment - Wind Farm Design - Blade Design & Tests - Wind Turbine Control - Smart Structure & CMS - Performance Tests - Offshore Wind Turbine Major Research Infrastructure - 10kW, 100kW, 1.5 & 2MW WTs - One(1) Offshore Demonstration Site - Two(2) Performance Test Sites 2MW Offshore Wind Turbine @ Jeju Island

4 Small Wind Test Small Wind Performance Test - Official Test Center since 2005 - Designated Test Site for Small Wind - Up to 100kW WT - Power, Load & Acoustic Emission 100kW WT 10kW WT

5 Large Wind Test Large Wind Performance Test - Official Test Center since 2009 - Designated Test Site - Up to 5MW WT (currently 2 & 3MW WT) - Power, Load & Acoustic Emission 1.5MW Wind Turbine @ KIER’s Jeju Island Site

6 National Agenda 2009 Energy Consumption : 66.8GW National Target of Renewable Energy Supply : 11% in 2030 - 100 billion USD (Supply : 86 billion USD, R&D : 14 billion USD) Action Plan : Green Home & Green Village Projects RPS (Renewable Portfolio Standard) will be in effect by 2012 Limitations : 1.Mountainous & complex terrain 2.Relatively low wind speed on land 3.Public acceptance

7 Wind Resource in Korea Average Wind Speed < 6.5m/s

8 Offshore Wind Power Offshore Windfarm Layout Saemangum s/s 345kV Gochang s/s 154kV 3 rd Phase Commercial 2 rd Phase Demo 1 rd Phase Pilot 3 rd Phase 2017 ~ 2019 Commercial 1.5GW (5MW x 300) 51.6 billion USD 1 st Phase 2011 ~ 2013 Pilot Scale 100MW (5MW x 20) 0.5 billion USD 2nd Phase 2014 ~ 2016 Demo Scale 900MW (5MW x 180) 27.7 billion USD

9 Supply Chain Blade : DACC(5MW, about 60m long blade), KMI(3MW, 44m long blade) Generator : HYOSUNG(5MW), HYUNDAI Heavy Industry(5MW) Cast Iron : TAEWOONG(GE, VESTAS, ENERCON), PSM(GE, SUZLON, GAMESA, VESTAS) Towers : Dongkuk S&C(VESTAS, ASSIONA, SIEMENS, ENERCON, GAMESA, GE)

10 Wind Turbine in Korea 2003 750kW Wind Turbine Development 2005 1.5MW Wind Turbine Development 2008 2MW Wind Turbine Development 2009 3MW Offshore Wind Turbine Development 2012 5MW Offshore Wind Turbine to be Developed 2013 7.5MW Wind Turbine to be Developed Development History M&A History 2009 DSME took over DeWind (U.S.A.) 2010 STX took over HARAKOSAN (Netherlands)

11 Wind Power Industry 9 Manufacturers 2MW, 2.5MW & 7.5MW 2MW 1.65, 2, 2.5MW & 5MW 3MW 750kW, 2MW & 5MW 100kW, 1.5MW & 2MW 750kW, 2MW & 5MW 3MW 2MW & 8MW

12 2009. 11 2.5MW Wind Turbine exported to CIELO (U.S.A.) Wind Power Industry

13 2011. 5 won 20MW Frisco Windfarm project 2011. 5 won 10MW windfarm from WEICAN (Canada) 2011. 6 built manufacturing factory in Nova Scotia in Canada

14 Wind Power Industry 2009. 4 exported 16MW WT to Finish Power (Finland) 2009. 9 exported 1.65MW WT 6 units to WAVE Wind (U.S.A.)

15 Windfarms in Korea Taegisan Windfarm, 2MW x 20Youngdeok Windfarm, 1.65MW x 24 Daekwanlyoung Windfarm, 2MW x 49 Youngyang Windfarm, 1.5MW x 41

16 Wind Turbine in Operation at King Sejong Station Thanks for your Attention