January 21, 2010 Project Status Report.  Introduction  Meeting Minutes Approval  Project Status Report  Other Business  Public Comments  Review.

Similar presentations


Presentation on theme: "January 21, 2010 Project Status Report.  Introduction  Meeting Minutes Approval  Project Status Report  Other Business  Public Comments  Review."— Presentation transcript:

1 January 21, 2010 Project Status Report

2  Introduction  Meeting Minutes Approval  Project Status Report  Other Business  Public Comments  Review of Action from Meeting  Scheduling of Next Meeting  Adjourn Page 2

3  Introduction  Meeting Minutes Approval  Project Status Report  Other Business  Public Comments  Review of Action from Meeting  Scheduling of Next Meeting  Adjourn Page 3

4  Budget & Timeline  Metrics Tracking and Reporting  Invitation To Negotiate (ITN)  Independent Validation and Verification (IV&V)  Workforce Services, Workforce Florida and Workforce Boards  Interviews with Other States  “To-Be” Process Review Workshop  Next Steps: Use Cases  Process Improvement Reviews Page 4

5 Page 5

6 Page 6

7 Page 7

8  Feasibility Study has targeted $43M in annualized savings  Begin to document the cost drivers behind those savings, identify the supporting metrics and begin a disciplined process for collecting those metrics  Plan to complete a Benefits Realization Strategy and Plan prior to Phase 3 kick-off (October 2010) Page 8

9  Approved to use existing available budget authority  Decision made to competitively procure the development of the ITN and Evaluation/Selection/Negotiation Strategy  RFQ currently under review Page 9

10  Ernst & Young contract currently being approved  Prepared to start next Monday Page 10

11  Project Description ◦ Conduct additional analysis into the Workforce Program as it relates to potential improvements that might be realized as part of the UC modernization effort ◦ Determining the possibility and plausibility of improving Workforce processes to provide better integration with the UC Program Page 11

12  February 9, 2010 ◦ Workforce & UC Integration Goals and Objectives  February 19, 2010 ◦ High Level As-Is Process Flow Document ◦ Plan and estimate for potential definition of To- Be process flows and corresponding requirements related to the UC system  February 28, 2010 ◦ Final high-level requirements for UC Page 12

13  Background ◦ Moving toward modernization for 10 years ◦ Presently in year 2 of a 5 year $150M effort for Tax and Benefits ◦ In-house development - 150+ project team ­ 15-20 dedicated SMEs ◦ Have broad requirements ­ Developing detailed requirements “Just In Time” through the Agile Methodology ◦ Technology driven initiative ­ Service Oriented Architecture (SOA) & Java Page 13

14  Lessons Learned ◦ Had multiple vendors for requirements and switched project managers ◦ Contracts were poorly managed ◦ Did not develop quality use cases ◦ Did not have an enterprise architecture group ◦ Should have hired skilled consultants as needed Page 14

15  Background ◦ 2002 defined requirements, use cases at a very high level - Issued RFP in 2003 ◦ After one year, realized that the project effort was underestimated by 100% ◦ Restarted detail design in 2007 ◦ Project team size ­ 12 SME’s for 12 functional areas who were responsible for getting additional resources from program areas and 30 UAT testers ­ 60 System Integrator (SI) staff Page 15

16  Lessons learned ◦ Business process changes are only now being defined. Should have done this initially Page 16

17  Background ◦ Benefits redesign phase began in 2005. Went to production in October 2007 ◦ Currently timely in all business areas, even with 3x normal workload ◦ Were focused on business vs. technical solution ◦ Project team ­ 30 agency SME’s & 12 agency technical staff ­ 30 SI developers; 30 SI technical staff ◦ Agency positions were not backfilled which created difficulties for Operations Page 17

18  Lessons learned: ◦ Entire organization must be committed to the goal ◦ Important to understand that there will be unavoidable risks ◦ Ensure that your staff is integrated and understand their clearly defined roles ◦ Workforce Integration: built open structures so that integrations can be developed at a later date Page 18

19  Background ◦ Benefit redesign timeline: January 2005 – March 2009 (included Katrina and EUC) ◦ Workflow was a major driving force ◦ Value added: number of claims takers down 30% and minimal incremental operational cost in ’09, but with triple the number of claims ◦ Project Team ­ 20 dedicated agency resources ­ Business analysts were assigned specific areas throughout development, implementation and testing ­ 40 SI associates dedicated to the project. Page 19

20  Lesson learned: ◦ Would have developed federal reports as we went along instead of waiting until the end to develop reports. Page 20

21  Lessons learned ◦ Broad consensus that we can begin with a transfer system from another state ◦ Project timeline of 4 years and $68M “feels” right ◦ Contract needs deliverable based milestones ◦ Key roles ­ Agency driven project – not System Integrator driven ­ SMEs to focus on functional knowledge ­ Business Analysts to pull operational vision together for continuity ­ System Integrator for technical and system expertise ­ Get agency technical staff involved early Page 21

22  Lessons learned con’t ◦ Create an incentive structure for SMEs assigned to the project ◦ Ensure that you have a sponsor who can change spending authority and make scope decisions ◦ Phased implementation approach ­ Lower project risk but can cause operational challenges working with two systems during the interim ­ Develop a transition plan and training plan to mitigate identified risks ◦ Get interdependent agencies involved early including the shared data center Page 22

23  The “To-Be” Process Flow Workshop was held January 6-7 with UC senior management in attendance  Great dialog from a business process viewpoint – not technological  Agreement on overall process vision ◦ Sign-off occurring this week as scheduled  Efforts underway to define Use Cases ◦ Based on Use Case training conducted in November Page 23

24  All incoming and outgoing correspondence will be scanned, indexed and available on-line in electronic format  The system will include a business-rules driven workflow engine used to create work items, manage work queues, and route work items between queues  The system will include Case and Document Management functionality to manage related work components and artifacts  Generic work queues will be established, as appropriate, to support the processing of unknown, misrouted, or incomplete work items  The system will include clearly defined roles and authorities for all users; every user will be assigned to a specific role

25  Employers, Claimants, and authorized third-parties will have system accounts, protected by appropriate security credentials, and all work items will be associated to those accounts  The system will maintain balances for all accounts and automatically recalculate balances based on the reversal or modification of prior actions  Claimants, Employers, and authorized third-parties will be able to opt for electronic communication  Email will be an accepted communication method for external parties (claimants, employers, and authorized third-parties) ◦ Communication will be in accordance with the preferred method (e.g., email notifications, fax, paper)

26  The system will not send sensitive information via email. Users will be notified documents are ready to be viewed using their online accounts. Access to documents will be controlled using appropriate security credentials  All claims, claim weeks, determinations, and payments will be traceable to funding sources and employer chargeability records  The system will create and maintain an online history of all activities related to a particular claimant, employer, or authorized third-party to include claims, claim weeks, determinations, and decisions

27 Page 27

28  Introduction  Meeting Minutes Approval  Project Status Report  Other Business  Public Comments  Review of Action from Meeting  Scheduling of Next Meeting  Adjourn Page 28


Download ppt "January 21, 2010 Project Status Report.  Introduction  Meeting Minutes Approval  Project Status Report  Other Business  Public Comments  Review."

Similar presentations


Ads by Google