1 15-05-2013 «BE-RF-PM» Updates on thermal tests Fabrizio Rossi
2
2 15-05-2013 «BE-RF-PM» Updates on thermal tests 2 2 SAFETY MEASURES PREVENTIVE ACTIONS 1.Implementation of AUL (Arret d’Urgence Local) for cutting electricity inside experimental test area (electricity is not cut from the water chiller) -> COMPLETED 2.Emergency lights in case of black out -> in progress 3.Access control badges for experimental area -> in progress CORRECTIVE ACTIONS 1.Flash panel for warning about tests with heaters -> COMPLETED 2.High temperature insulation for electric wires connected to heaters -> COMPLETED 3.Dedicated support for electric wires -> COMPLETED 4.Time-delay relay for control valves -> COMPLETED 5.Independent temperature display inside the lab for visualizing temperature close to heaters -> COMPLETED 6.Daily schedule agreed and posted at the entrance -> COMPLETED
3
3 15-05-2013 «BE-RF-PM» Updates on thermal tests 3 3 PREVENTIVE ACTIONS: AUL
4
4 15-05-2013 «BE-RF-PM» Updates on thermal tests 4 4 CORRECTIVE ACTIONS Flash panels High temperature insulation and dedicated supports for electric wires Independent temperature display inside laboratory Daily schedule at the entrance of the laboratory Time-delay relay for control valves
Similar presentations
© 2024 SlidePlayer.com Inc.
All rights reserved.