Presentation is loading. Please wait.

Presentation is loading. Please wait.

INTERNATIONAL AGREEMENTS PARTICIPATION AND DISSEMINATION RULES

Similar presentations


Presentation on theme: "INTERNATIONAL AGREEMENTS PARTICIPATION AND DISSEMINATION RULES"— Presentation transcript:

1 INTERNATIONAL AGREEMENTS PARTICIPATION AND DISSEMINATION RULES
Legal Framework EC TREATY INTERNATIONAL AGREEMENTS PARTICIPATION AND DISSEMINATION RULES FRAMEWORK PROGRAMME CONTRACTS SPECIFIC PROGRAMMES GUIDELINES ON EVALUATION AND SELECTION PROCEDURES Other relevant EC Regulations FINANCIAL REGULATION WORK PROGRAMMES & Calls for proposals

2 Guidelines Will provide supplementary information and guidance notes:
Financial guidelines Negotiation guidelines Consortium agreement guidelines Project management guidelines

3 General Principles Reflect requirements of the Legal Framework
Simplification No different categories of contractors Reduction of the number of contracts Collective approach Greater flexibility the Work Programme may adjust Rules flexibility in the composition and changes to consortium Greater autonomy for participants

4 The instruments Integrated Projects: new Networks of excellence new
RULES APPLIES TO ALL Integrated Projects: new Networks of excellence new Specific targeted research or innovation projects Specific research projects for SMEs Co-operative research projects Collective research projects new Integrated infrastructure initiatives new Actions to promote human resources and mobility (Some are new) Co-ordination actions Specific support actions Article 169 new (specific rules to this instruments)

5 Contract Structure Core contract (standard with specifics of project)
Annex I (technical tasks - the “project”) Annex II General Conditions (applicable to every instrument) Annex III Instrument specific provisions (specific to instrument)

6 Contract Structure Annex IV - Form A Consent of contractors identified in the core-contract (article 1.2) to accede to the contract. To be signed by the contractor concerned and by the coordinator. Annex V - Form B Accession of new legal entities to the contract. To be signed by the new contractor concerned and by the coordinator Annex VI - Form C Financial statement per activity. Specific to each Instrument and/or type of action. To be filled periodically by each contractor

7 Core-Contract Structure
Art Scope Art Constitution of the Consortium Art Evolution of the consortium Art Entry into Force of the Contract and Duration of Project Art Community financial contribution Art Reporting periods Art Reports Art Payment modalities Art Special clauses Art Amendments Art Communication Art Applicable law Art Jurisdiction Art Annexes forming an integral part of this contract

8 Annex II - General conditions Structure
Article II.1 - Definitions Part A: Implementation of the Project Section 1 - Implementation and deliverables Section 2 - Termination of the contract and responsibility Part B: Financial Provisions Section 1 - General financial provisions Section 2 - Controls, recoveries and sanctions Part C: Intellectual Property Rights

9 Annex II - General Conditions Structure
Part A: Implementation of the Project SECTION 1 - IMPLEMENTATION AND DELIVERABLES Art.II Activities Art.II Performance obligations Art.II Force majeure Art.II Suspension and prolongation of the project Art.II Subcontracting Art.II Reports and deliverables Art.II Evaluation and approval of reports and deliverables Art.II Confidentiality Art.II.10 - Communication of data Art.II.11 - Information to Member States and Associated States Art.II.12 - Publicity Art.II.13 - Liability Art.II.14 - Assignment

10 Annex II - General Conditions Structure
Part A: Implementation of the Project SECTION 2 - TERMINATION OF THE CONTRACT AND RESPONSIBILITY Art.II Termination of the contract and participation of contractors Art.II Termination for breach of contract and irregularity Art.II Technical collective responsibility Art.II Financial collective responsibility

11 Annex II - General Conditions Structure
Part B: Financial provisions SECTION 1 - GENERAL FINANCIAL PROVISIONS Art.II.19 - Eligible costs of the project Art.II.20 - Direct costs Art.II.21 - Indirect costs Art.II.22 - Cost reporting models Art.II.23 - Receipts of the project Art.II.24 - Community financial contribution Art.II.25 - Reimbursement rates Art.II.26 - Audit certificates Art.II.27 - Interest yielded by pre-financing Art.II.28 - Payment modalities

12 Annex II - General Conditions Structure
Part B: Financial provisions SECTION 2 - CONTROLS, RECOVERIES AND SANCTIONS Art.II.29 - Controls and audits Art.II.30 - Liquidated damages Art.II.31 - Reimbursement to the commission and recovery orders

13 Annex II - General Conditions Structure
Part C: Intellectual Property Rights Art. II.32 - Ownership of knowledge Art. II.33 - Protection of knowledge Art. II.34 - Use and dissemination Art. II.35 - Access rights Art. II.36 - Incompatible or restrictive commitments

14 Participation New Every legal entity that contributes to the project (incl. Project Managers) General Rule: Participant = contractor Every legal entity contributing to a project must have a contractual link with the Community Exceptional cases: subject to very restrictive rules Third parties identified in Annex I Subcontractors

15 Third parties identified in Annex I
Participation Third parties identified in Annex I In most of the cases they do not participate, they simply make their resources available to a contractor, this is not a case of participation but only a question of eligibility of the cost of these resources In exceptional cases: “participation” of members of entities such as EEIG,UMR, SMEs Associations: these entities are contractors (EEIG, UMR) their members can do some of the work on the project even though they are third parties contractor and third parties must have a previous agreement, normally the constitution the third parties, the agreement and the tasks must be identified in Annex I

16 Participation Subcontracting
Contractors shall ensure that the work to be performed can be carried out by them. Exception: where it is necessary to subcontract certain elements of the work, this should be clearly identified in Annex I. Minor services may be subcontracted: which do not represent core elements of the project which cannot be directly assumed by contractors where necessary for the performance of the project

17 Signature and entry into force
Contractual link of all contractors with the Commission New Contract enters into force upon signature of coordinator and Commission All the contractors are identified in the core contract [Art. 1.2] Coordinator must ensure other contractors sign within delays Distribution of advance - Several options available: minimum number of participants/all participants Evolution of consortium possible: where one or more does not sign the Form A [article 2] in case of enlargement (new contractors) [article 3] Project begins in the date established in the contract (this can be before the contract enters into force but usually later)

18 Amendments Art.10 of Core Contract & Art.8 of Annex II
Request in writing New at the request of the coordinator, deemed to act on behalf of the consortium New Tacit amendments with implicit agreement of the Commission within 6 weeks only for modification and evolution of the consortium and for technical reports New in IP/NoE, enlargement of the consortium to new contractors and new activities may be foreseen. This enlargement follows a competitive call launched by the consortium with evaluation of proposals by external experts

19 New: Collective responsibility of the contractors
LIABILITY (1) New: Collective responsibility of the contractors Mechanism by which a contractor may be held liable, technically and/or financially, fully or partially, for the action of another contractor Why? Reinforce the protection of the financial interests of the Community, both quantitative (only pay what is due to be paid) and qualitative (ensure that the project continues) Consequence of FP6 principle of “autonomy of the consortium”: if the money is granted to the consortium, which decides on its allocation, then the consortium as a whole is to be held liable

20 LIABILITY (2) Implementation: applied as a last resort
Breach of contract Depending on the nature of the breach, the consortium will be invited to find the appropriate solution (technical responsibility) If no solution is found, the defaulting contractor is excluded and the consortium is requested to continue the project (technical responsibility with financial consequences) If the consortium refuses to perform: 1 - the contract is terminated 2 - the consortium is requested to reimburse money owed by the defaulting contractor (collective financial responsibility)

21 LIABILITY (3) Implementation: limitations
Limited in proportion to the participant’s share of costs in the project, up to the total payment they are entitled to receive IOs, public bodies or entities guaranteed by MS/AS solely responsible for their own debts Exceptions for specific actions for SME’s, fellowships, duly justified cases of specific support actions Without prejudice to civil and criminal actions to be launched against the defaulting contractor

22 LIABILITY (4) Additional impacts Raises awareness among contractors:
1 - constitution of the consortium 2 - projects with real and lasting common interests (avoid artificial transnational projects) 3 - establishment of internal auto-controls and checks and balances within the consortium Limits systematic requests for bank guarantees and performance of ex-ante financial controls: 1 - as foreseen in the new financial regulations 2 - depending on the impact of the limitations (risk assessment - to be detailed in “Guidelines on negotiations”)

23 Financing : what ? Community Financial Contribution (Arts 5 and II.24)
Based on activities: Articles II.2 and II.25 Based on costs: Articles II.19, II.20 and II.21 Based on costs reporting models: Art II.22 Confirmed by an audit certificate: Art II.26

24 Financing Grant for integration Grant to the budget Flat-rate
Networks of excellence  Integrated Projects  Specific targeted research projects  Specific research projects for SMEs  Integrated initiatives relating to infrastructure  Actions to promote human resources & mobility   Coordination actions  Specific support actions  

25 Other specific support activities
Financing Type of activity (a) Research and technological development (including innovation related activity) Demonstration Training Other specific support activities New Consortium Management : costs reimbursed up to 100% within the limit of 7% of Community contribution (AC contractors “apply FCF”)

26 Financing Type of activity (b)

27 Financing Costs New principles:
1 - cost categories are replaced by conformity to contractors’ own accounting rules and legal environment 2 - simplify the eligibility criteria 3 - focus resources on the reality and the necessity of the cost, rather than on formality (cost categories) Therefore, costs must be : actual, economic and necessary for the project incurred during the duration of the project (exception: costs of the final reports) recorded in the accounts (or third parties) and must exclude indirect taxes, duties, interests, costs reimbursed in respect of another Community project, and not give rise to profit

28 Financing Cost Reporting Models
FC: actual direct and indirect costs (not available for Coordination Actions and Specific Support Actions) New FCF (variant of FC): actual direct costs + flat rate for indirect costs (20% of total actual direct costs, except costs of subcontracts - all instruments) AC: actual additional direct costs + flat rate for indirect costs (20% of total actual additional direct costs, except costs of subcontracts - all instruments)

29 Financing SMEs, non- commercial or non-profit organisations established either under public or private law, international organisations: FC/FCF Physical persons: AC mandatory Private companies (other than above): FC AC: only for those non- commercial or non-profit organisations established either under public or private law or international organisations that do not have an accounting system that allows the share of their direct and indirect costs relating to the project to be distinguished. General Rule: a legal entity applies the same cost model in ALL contracts established under FP6 except may move from AC to FCF/FC or from FCF to FC (“one way ticket”)

30 Financing Costs under FC/FCF
Direct costs must be eligible costs that can be related directly to the project Indirect costs must be : for FC eligible costs determined by the contractor, in accordance with its usual accounting practices and the definition of indirect costs [article II.21] for FCF a flat rate is applied to the direct costs to cover indirect costs.

31 Indirect costs consist of a flat rate applied to the direct costs.
Financing Costs under AC Direct additional costs must be direct costs additional to the normal recurring costs of the contractor and not covered by any other sources of funding.Three possibilities of charging costs related to personnel: personnel with a temporary contract to complete a doctorate ; personnel with a temporary contract for working under the Community contract concerned ; personnel whose employment contract depends full or in part on additional external financing. Indirect costs consist of a flat rate applied to the direct costs.

32 Financing Receipts Three kinds of receipts must be taken into consideration in order to avoid any possibility of profit: Financial transfers or their equivalent to the contractor from third parties ; Contributions in kind from third parties; Income generated by the project. In the first two cases (financial transfers or contributions in kind), these endowments are considered as receipts of the project if the third party has provided them specifically to be used in the project. If, on the other hand, these endowments are at the discretion of the contractor they are not to be considered as receipts.

33 Financing Receipts In the first two cases, where contributions from third parties are used for the project by the contractor, the latter is required to inform the third party of this use and in accordance with the national legislation or practice in force. In the case of income generated by the project itself: General rule: any income generated by the project itself, including the sale of assets bought for the project, are considered as income to the project (receipts) Derogation: income generated by the use of the knowledge resulting from the project is not considered as a receipt

34 Reports and deliverables
Financing Reports and deliverables All reports and deliverables shall be submitted within 45 days of the end of the period in question. The project is divided into reporting periods of 12 months for IP and NOE For other instruments, reporting periods are established on an ad hoc basis in the contract P1: from month 1 to month X P2: from month X+1 to month Y P3: from month Y+1 to month Z final: from month N+1 to the last month of the project

35 Reports and deliverables
Financing Reports and deliverables The consortium will submit the following reports to the Commission: For each reporting period: a periodic activity report a periodic management report a report on the distribution between contractors supplementary reports required by Annex to this contract an audit certificate when required

36 Reports and Deliverables
Financing Reports and Deliverables In addition to the periodic reports of the last period, for the last period: a final activity report a final management report supplementary reports required by Annex to this contract a report on the distribution between contractors made after the end of the project of the Community financial contribution - shall be 60 days after receipt of the final tranche

37 Financing Audit certificates Article II.26
each contractor shall provide an audit certificate prepared and certified by an external auditor (for public bodies - competent public officer) for each period for which an audit certificate is required (article 7 - option 2) every 12 months for IP/NoE (article 7 - option 1) where requesting a Community financial contribution exceeding € for a specific reporting period, even though an audit certificate is not required for this specific period

38 Financing : how ? Payment Modalities
Periodic pre-financing (based on the applicable periodicity) The Community financial contribution is paid to the coordinator on behalf of the contractors: the consortium decides on the allocation of each tranche of its between the contractors (consortium agreement)

39 Financing Payment modalities
The Community financial contribution shall be paid in accordance with the provisions of Article 8 and II.28. Differences between: 1] one single reporting period 2] several reporting periods - with an audit certificate for each period - without an audit certificate for each period 3] one single reporting period - lump sum

40 Payments and reporting schedule for an IP (example of a 4 year contract)
Activity report Reported costs Activity report Detailed work plan Reported costs Adjusted advance Activity report Detailed work plan Reported costs Adjusted advance Activity report Detailed work plan Reported costs Adjusted advance Detailed work plan Initial advance Months

41 Payments and reporting schedule for a STREP, CA or SSA (example of a 3 year contract)
Final activity report Final payment Reported costs + audit certificate (mandatory) Intermediate pre-financing or payment NB: impact on the total pre-financing Periodic activity report (mid-term review : optional) Reported costs + (audit certificate if required) Detailed work plan Initial advance Months

42 1 - assessment of the scientific outputs
Controls (1) reinforce scientific monitoring and ex-post financial controls Simplified and streamlined ex-ante controls due to the collective responsibility Simplified and streamlined day-to-day financial management due to the audit certificates and the new approach on eligible costs (no more formal conformity with cost categories) Reorient resources in qualitative monitoring and control: 1 - assessment of the scientific outputs 2 - appraisal of the necessity of the costs with regards to these outputs

43 Controls (2) How? New: continuous monitoring by Commission with external experts (mandatory for IP and NoE), based on simplified procedures (no public procurement) New:periodical reviews of results achieved and expenditure made - go/no-go procedure (12 months basis for IP & NoE - ad hoc for other instruments) Technical (incl. ethical), technological, and financial audits

44 Sanctions Autonomy implies accountability
New: in case of irregularity in a contract... 1 - exclusion from the contract 2 - exclusion from OTHER FP6 contracts, and from other Community policies 3 - ineligible to participate in FP6 activities, and from other Community policies New: liquidated damages in case of financial overstatement Without prejudice to civil and criminal sanctions

45 Intellectual Property Rights (IPR)
Developed on the basis of Feedback from FP5 Features of the “new instruments” contractors may leave/join during the project “larger” projects

46 Principles Consistency with FP5 (similar concepts) Simplification
 New Same IPR rules for  all instruments (fewer exceptions)  New Same IPR rules for all contractors Increased certainty, in particular regarding access rights (restricted to what is necessary) Increased emphasis on the management of knowledge and IP (especially new instruments)

47 General Concepts Definitions: no major change compared to FP5
“knowledge”, “pre-existing know-how”, “use”, “dissemination”, ... Ownership: no major changes compared to FP5 resides with the contractor (incl. JRC) generating knowledge exception for SME actions : cooperative research - SMEs own results not the “RTD Performers” collective research - SME associations own results transfer of ownership: prior notice to other participants + Commission (possible objection within 30 days) public procurement (Commission owns results)

48 General Concepts - Protection
Where there is commercial application and subject to legitimate interests, it is a requirement to protect Where there is no protection, Commission may protect Publication allowed if not detrimental to protection prior notice to Commission + other contractors (possible objection within 30 days) Use / dissemination Obligation to use and disseminate Commission may disseminate itself if needed

49 Access Rights General principles
New Granted on written request, access rights for use of another’s results only where necessary (not by right) No sub-licensing (unless explicitly agreed + possible optional clause for software) Obligatory Access Rights between contractors limited to what they really need (either for carrying out the project or for using their own knowledge) but broader Access Rights may be freely negotiated Access Rights granted to third parties : Commission may object

50 Access Rights New features
Feedback from FP5: need for pre-existing know-how (Pre-Existing Know How ) to be better safeguarded New Possibility for a contractor to exclude specific Pre-Existing Know How from the obligation to grant Access Rights to the others with the agreement of all participants before the contractor concerned signs the contract (or before entry of a new contractor)

51 FP6 System of Access Rights
Access rights to Access rights to pre-existing know-how knowledge If a contractor needs them for carrying out its own work under the project For carrying out the project Royalty-free unless otherwise agreed before signing the contract Royalty-free If a contractor needs them for using its own knowledge For use (exploitation + further research) Non-discriminatory conditions to be agreed Royalty-free unless otherwise agreed before signing the contract Possibility for participants to agree on exclusion of specific pre-existing know-how before signature of the contract (or before entry of a new participant)

52 Consortium Agreement WHY ? (1)
1 - Mandatory unless excluded by the call for proposals 2 - Management of the consortium: distribution of funds paid to the consortium (via the coordinator) no automatic pre-allocation of the funds among contractors: to be decided by the consortium evolution of the work programme organisation of work to be carried out (sub-projects) reports presented and submitted by the consortium (via the coordinator) evolution of the consortium’s composition (modification)

53 Consortium Agreement WHY ? (2)
3 - IPR issues: should be agreed before signature of the contract (mandatory for specific Pre-Existing Know How exclusion) 4 - Global Risk Management: collective responsibility technical implementation of the action = collective responsibility of the contractors consortium to deal with breach of contract / non-performance and imposition of financial collective responsibility and any financial security necessary for same

54 Consortium Agreement Issues Decision-making process
governance may range from “1 participant, 1 vote” to “elective dictatorship”, via the shareholder approach IPR - ensure that agreements necessary for the implementation of the project have been reached - exclusion of background/sideground - initiate common strategy on dissemination/use/protection + search for industrial partners Global Risk Management - establish internal auto-control and a checks and balances mechanism (periodic distribution of the funds, progress reporting, etc). - specific issues regarding competitive calls, costs less than EC funding etc for specific instruments


Download ppt "INTERNATIONAL AGREEMENTS PARTICIPATION AND DISSEMINATION RULES"

Similar presentations


Ads by Google